The acronym ACO as used in this
instruction could refer to either Corporate Administrative
Contracting Officer (CACO), Divisional Administrative
Contracting Officer (DACO) or Administrative Contracting
Officer unless specified otherwise.
For the special Programs
Directorate, the approval authority for actions herein
remains with the appropriate CMO Contracts director.
DACOs and CACOs assigned to the Special Programs Directorate
will not be realigned to the cost and Pricing Center.
1. Receive Certified Proposal. The ACO shall ensure the contractor submits
the required certified final indirect cost rate proposals
(FAR
52.216-7) within six months following the expiration of each of
its fiscal years.
1.1. The ACO should only grant
contractors due date extensions if the contractor submits a written
request for an extension based on exceptional circumstances (FAR
42.705-1(b)).
1.2. (ND) If the ACO grants an extension, the ACO shall
prepare a written memorandum for record (MFR) to document the
exceptional circumstances and rationale for approving the
extension. The ACO shall provide DCAA a copy of the
MFR.
1.3. (ND) If
DCAA notifies the ACO that the contractor's certified final indirect
cost rate proposal is late or inadequate, the ACO
shall work with DCAA to obtain an adequate proposal from the
contractor.
1.4. Whenever there
are late or inadequate proposals, the ACO should take aggressive
actions to obtain adequate proposals including:
1.4.1.
Establishing unilateral rates for late or uncertain proposals (FAR
42.703-2(c)(2), Certificate of Indirect
Costs).
1.4.2.
Decrementing provisional billing rates for unsupported costs (FAR
31.201-2(d), Determining
Allowability).
1.4.3. Establishing contract withholds for significant
accounting system or related internal control deficiencies (DFARS
242-7502(a)(4), Contractor Accounting Systems and Related
Controls).
1.5. (ND) ACOs shall obtain the CMO Contracts
Director's written approval if they do not intend to accept DCAA's
unilateral rate recommendations or intend to grant a contractor an
extension to the proposal due date. LATEST CHANGE Corporate
Administrative Contracting Officers (CACO) and Divisional Contracting
Administrative Officers (DACO) shall obtain written approval from the Director of Corporate/Divisional Administrative
Contracting Officer Group if they do not intend to accept DCAA's unilateral rate
recommendations or intend to grant a contractor an extension to the
proposal due date. If DCAA disagrees with the ACOs
decision regarding either action, the action will be subject to the
resolution of DCAA/DCMA disagreements process in paragraph 5 of the
Contract Management Boards of Review Instruction.
2. Receive DCAA Audit. The ACO shall request and receive a DCAA audit of the contractor's certified final indirect cost rate
proposal.
3. Determine if ACO or
DCAA determines the rates. The ACO shall follow the
procedures at FAR
42.705-1 and 42.705-2 to determine whether the rates are subject to determination by the
ACO or DCAA.
4.1.1.
The ACO shall develop the
pre-negotiation objectives (PNO) (FAR
15.406-1). The PNO
represents the ACO's initial negotiation position. The scope
and depth of the analysis supporting the PNO should be directly
related to the dollar value, importance, and complexity of the
contractor's overall rates and individual elements of costs.
4.1.2. (ND) The ACO shall fully
consider all DCAA questioned, unsupported, and unresolved costs
and obtain any clarifications from DCAA needed to understand
the audit recommendation and
findings.
4.1.3. The ACO shall not resolve any
questioned costs until obtaining adequate documentation on the cost
and DCAA's opinion on the allowability of the costs (FAR
42.705-1 (b)(4)(i) and
(ii)).
4.1.4. The ACO should negotiate and finalize all local issues
under their cognizance while waiting for corporate or other
flow-down
costs.
4.1.5. (ND)
The ACO shall document in the
PNO:
4.1.5.1.
An affirmative statement that the ACO
agreed or disagreed with each finding and recommendation made by
DCAA or DCMA specialists (e.g., price/cost analyst, engineer,
counsel) and whether or not the assessment of any penalties and
interest is appropriate. (See paragraph 6 below for more
information about penalties and interest.)
4.1.5.2.
Sound rationale for resolving each finding
and recommendation made by DCAA or DCMA technical specialists and
whether or not penalties and interest should be assessed. The rationale must demonstrate that the ACO has considered
all appropriate FAR, DFARS, and DCMA Instructions related to the
issue raised or questioned by DCAA, e.g., cost principles, cost
accounting standards.
4.1.6.
The ACO shall invite
contracting offices having significant dollar interest to
participate in the in preliminary discussions of critical issues
(FAR
42.705-1(b)(3)). Individuals or
offices that have provided a significant input to the Government
position should also be invited to participate.
4.1.7. (ND)LATEST CHANGE The ACO shall obtain approval of the PNO
from the CMO Contracts Director, and any required Contract
Management Boards of Review approvals, before
entering into negotiations. The CACO or DACO shall
obtain approval of the PNO from the Director of Corporate/Divisional Administrative
Contracting Officer Group, and any
required Contract
Management Boards of Review approvals, before
entering into negotiations. The CMO Contracts Director may
delegate authority to approve the PNO to a level no lower than the
contract team supervisor/leader.
4.1.8.
(ND)LATEST CHANGE The CMO Contracts Director
shall verify that the ACO followed the procedures for resolving reportable
audit before approving the PNO. The Director of Corporate/Divisional
Administrative Contracting Officer Group shall verify that the CACO or DACO followed the procedures
for resolving reportable
audit before approving the PNO.
4.2. Negotiate Rates.
4.2.1. Final overhead negotiations
will be completed within a 27 or 36 month
cycle for major and non-major contractors, respectively.
DCAA's definition of a major contractor (over $100 million of
auditable dollar volume) will be used in determining whether a
location is major or non-major.
4.2.2.
The ACO shall invite contracting
offices having significant dollar interest to participate in the
negotiation (FAR
42.705-1(b)(3)). The ACO, whenever
possible, should invite the auditor to serve as an advisor at
negotiations (FAR
42.705-1(b)(4)(ii)).
4.2.3.
If the ACO and contractor
are unable to reach agreement on the final annual indirect costs
rates (FAR
52.216-7(d)(4)):
4.2.3.1.
The failure to reach
agreement is a dispute within the meaning of the Disputes clause
(See Contract
Claims and Disputes
Instruction).
4.2.3.2.
The ACO shall unilaterally
establish the rates.
4.3. Execute Written Indirect Rate
Agreement and PNM.
4.3.1. The ACO shall prepare a written rate agreement that specifies (FAR
52.216-7(d)(3)):
4.3.1.1. T
he bases to which the rates apply,
4.3.1.2.
The periods for which the rates apply,
4.3.1.3.
Any specific indirect costs items
treated as direct costs in the settlement,
4.3.1.4.
The agreed upon final indirect costs
rates,
and
4.3.1.5.
The affected contracts and/or
subcontracts, identifying any with advance agreements or special
term and the applicable rates.
4.3.2.
The ACO shall prepare a PNM
containing (FAR
42.705-1(b)(5)
4.3.2.1. (ND)
An affirmative statement
that the ACO agreed or disagreed with each finding and
recommendation made by DCAA or DCMA Specialists (e.g., price/cost
analyst, engineer, counsel), and whether or not the assessment of
any penalties and interest is appropriate. (See paragraph
6 below for more information about penalties and interest.
)
4.3.2.2. ( ND)
Sound rationale for resolving each finding and
recommendation made by DCAA or DCMA Specialists, and whether or not
the assessment of any penalties and interest is appropriate.
The rationale must demonstrate that the ACO has considered all
appropriate FAR, DFARS, and DCMA Instructions related to the issue
raised or questioned by DCAA, e.g., cost principles, cost accounting
standards.
4.3.2.3.
Reconciliation
of all costs questioned with identification of items and amounts
allowed or disallowed in the final settlements as well as the
disposition of period costs or allocability issues including the
assessment of any penalties and
interest.
4.3.2.4. Reconciliation of all costs that were
considered unallowable and the respective
amounts of the disallowance including the assessment of any
penalties and
interest.
4.3.2.5.
Identification of cost or pricing data
submitted during the negotiations and relied upon in reaching
settlement including the assessment of any penalties and
interest.
4.3.3. (ND) The ACO shall obtain approval of the
written agreement and PNM from the CMO Contracts Director, and any
required Contract
Management Boards of Review approvals, before signing the rate
agreement and PNM. LATEST CHANGE The CACO or DACO shall obtain approval
of the written agreement and PNM from the Director of Corporate/Divisional Administrative
Contracting Officer Group, and any
required Contract
Management Boards of Review approvals, before
signing the rate agreement and PNM. The
CMO Contracts Director may delegate authority to approve the action to a
level no lower than the contract team supervisor/leader.
4.3.4. (ND) The CMO
Contracts Director shall verify that the ACO followed the procedures
for dispositioning
reportable audit before approving the PNM. LATEST CHANGE The Director of Corporate/Divisional Administrative
Contracting Officer Group shall verify that the CACO or DACO
followed the procedures for dispositioning
reportable audit before approving the PNM.
4.4. Distribute Rate Agreement and PNM
(FAR
42.706)
4.4.1. The ACO shall promptly distribute executed
copies of the rate agreement to the contractor.
4.4.2.
The ACO shall promptly distribute
executed copies of the rate agreement and PNM to each affected
contracting office and DCAA.
4.4.2.1. (ND) The ACO shall document in the
contract file, the date and method of transmittal of the PNM to
DCAA.
5. DCAA Negotiates Rates. If
DCAA is unable to reach agreement with the contractor, DCAA will
issue a DCAA Form 1, Notice of Contract Costs Suspended and/or
Disapproved. When the ACO receives a DCAA Form 1, the ACO shall follow the procedures in 4 above to
negotiate the rates.
6.1. If DCAA recommends
penalties for unallowable costs, the ACO shall (FAR
42.709-2):
6.1.1. Determine
whether the penalties in paragraph 6.2. should be assessed;
6.1.2. Determine whether such penalties should be waived
pursuant to 42.709-5;
and
6.1.3. Refer
the matter to the appropriate criminal investigative organization
for review if there is evidence that the contractor
knowingly submitted unallowable costs (see Fraud, Waste &
Abuse Instruction).
6.2.1. If the indirect cost is expressly
unallowable under a cost principle in the FAR or DFARS that defines
the allowability of specific selected costs, the penalty is equal to
(FAR
42.709-1(a)(1)):
6.2.1.1. The amount of the disallowed costs
allocated to contracts that are subject to penalties for which an
indirect costs proposal has been submitted; plus
6.2.1.2. Interest on the paid portion, if
any, of the disallowance.
6.2.2. If the indirect cost was determined to
be unallowable for that contractor before proposal submission, the
penalty is two times the amount in paragraph
6.2.1.1. (FAR
42.709-1(a)(2)). Prior
determinations of unallowability may be evidenced by (FAR
42.709-3(b)):
6.2.2.1. A
DCAA Form 1, Notice of Contract Costs Suspended or Disapproved, or
any similar notice which the contractor elected not to appeal and
was not withdrawn by the cognizant Government agency;
6.2.2.2. A contracting officer final decision
which was not appealed;
6.2.2.3. A prior executive agency Board of
Contract Appeals or court decision involving the contractor, which
upheld the cost disallowance, or
6.2.2.4. A determination or agreement of
unallowability under FAR
31.201-6.
6.3. Assess Penalties and Interest
6.3.1. Unless a waiver is granted pursuant to paragraph
6.4. below, the ACO shall assess the appropriate type of penalty
in paragraph
6.2. above.
6.3.2. If the indirect cost is expressly
unallowable, the ACO shall compute the applicable interest using the
procedures at FAR
42.709-4.
6.3.3. To assess the penalties, the ACO shall
issue a final decision (see FAR
33.211) which includes a demand for payment of any penalty
assessed. The letter shall state that the determination is a
final decision under the Disputes clause of the contract.
Demanding payment of the penalty is separate from demanding
repayment of any paid portion of the disallowed
cost.
6.4.1. If the indirect cost is expressly
unallowable, the ACO shall only waive the penalties when (FAR
42.709-5):
6.4.1.1. The contractor withdraws the
proposal before the Government formally initiates an audit of the
proposal and the contractor submits a revised proposal. An
audit will be deemed to be formally initiated when the Government
provides the contractor with written notice, or holds an entrance
conference, indicating that audit work on a specific final
indirect cost proposal has
begun;
6.4.1.2. The amount of the unallowable
costs under the proposal which are subject to the penalty is $10,000
or less (i.e., if the amount of expressly or previously determined
unallowable costs which would be allocated to the contracts
specified in FAR
42.709(b) is $10,000 or less);
or
6.4.1.3. The contractor demonstrates,
to the cognizant contracting officer's satisfaction,
that:
6.4.1.3.1. It has established policies and
personnel training and an internal control and review system that
provide assurance that unallowable costs subject to
penalties are precluded from being included in the contractor's
final indirect cost rate proposals (e.g., the types of controls
required for satisfactory participation in the Department of Defense
sponsored self-governance programs, specific accounting controls
over indirect costs, compliance tests which demonstrate that the
controls are effective, and Government audits which have not
disclosed recurring instances of expressly unallowable costs);
and
6.4.1.3.2. The unallowable costs subject to
the penalty were inadvertently incorporated into the proposal; i.e.,
their inclusion resulted from an unintentional error,
notwithstanding the exercise of due care.
7. Maintain Etools
Database. (ND) ACOs are responsible for the
accuracy of data entries in the eTOOLS Overhead Negotiations
database. The status of each step in the settlement process is
updated as needed to keep the information current. The use of
the database is mandatory for ACO negotiated and audit determined
contractors.
Competencies/Certifications
The ACO shall be a Warranted Contracting Officer.
Contract Administrators, Price Analysts and other specialists
should be DAWIA-certified in accordance with the position held.
Training Matrix
Final Overhead
Rate Training Matrix
What TASKS are
required to
accomplish this
process?
Methods of training
On-the-Job Training (OJT)
Computer Based Training (CBT)
Course (Commercial, College/
Vocational)
Contractor Sponsored Training
Guidebooks
DCMA Developed
Administrative Task (The task is wholly enabled by the
contents of the instruction and requires no training
intervention)