PIs are appointed to
lead PSTs for all DOD ACAT I, II & III programs, and comparable NASA or other
civilian agency programs.
1. Team Structure - When a major
program contract is awarded, CMO management identifies a PI, and based on
program objectives, challenges, and desired outcomes, determines the technical
specialist support required. PST members represent the full range of
Contract Management disciplines, including the Administrative Contracting
Officer (ACO), Contract Administrator (CA), Cost/Price Analyst, Property
Administrator, Engineer, Software Engineer, Industrial Specialist, Earned Value
Management Analyst, Quality Assurance Specialist, Software Quality Assurance
Specialist, Contract Safety Specialist, and Transportation and Packaging
Specialist. If the program requires EVM analysis, every effort must
be made to identify and assign overall EVM responsibility on the PST to an
individual that has the necessary earned-value management
experience/training. The PI is the PST Leader and is responsible for
ensuring the PST functions as a cohesive unit, providing timely insights,
actions, and recommendations to the PM. The PI provides input to
PST member supervisors on the level of support provided by the individual toward
PST efforts. PST members may have a matrix relationship with the PI
and remain under the supervision of their respective
supervisors.
1.1. Appointments - CMO Commanders
appoint PIs and PST members. Factors to consider in selecting individuals to
serve as PIs include: leadership abilities, certification, knowledge and
experience in contract and program management, ability to work with the PM at
the program IPT level, and specific acquisition program experience. PST
membership is dependent on the nature of the contract and specific program
requirements and objectives.
1.2. Memorandum of
Agreement (MOA) - An MOA is desired for all ACAT I, II & III Programs, as
well as non DoD programs of similar magnitude, receiving DCMA program
support. Because the MOA documents our commitment to the PMO, every effort
should be made to secure a bilateral document of the agreement. MOAs need
not be extensive. A typical MOA can be:
- A simple one or two page memorandum
executed by the PM and CMO Commander identifying what DCMA will do for the
program office, and why those activities are important to the program, forms
the core of the MOA.
- An attachment or appendix listing the
DCMA resources to be utilized (i.e., the personnel making up the PST and
SPST), their roles and contact information, and points of contact within the
PMO and the prime contractor's organization, provides the "who"
details.
- The surveillance plan comprises the
second attachment or appendix, and provides the "what" we will do in support
of the program, along with when, where, and how those activities will
occur.
1.2.1. Outcome Based MOAs - The focus of our
program support activities revolves around mitigating program risk. Each
program is burdened with a unique blend of risk elements. PMs face cost,
schedule, and technical challenges that endanger their programs. These
challenges result in a watch list for the PM. There are some risk elements
on the list that DCMA can help manage and others that are beyond our ability to
influence. The MOA should identify those risk elements on the watch list
where the PM requires our assistance in managing. In addition to those
risks facing a PM regardless of which contractor is selected as prime, there are
those risks associated with doing business with a given contractor. (See
the Supplier Risk Management Chapter.) Those risks are identified by the
PST functional specialists and documented in RAMP. The resulting Risk
Management Plan (RMP) documents "how" DCMA will strive to manage supplier
risk. The surveillance plan attached to an MOA, then, is an amalgam of
risk management activities derived from the PM's watch list and synopsized
extracts from the RMP.
1.2.2. MOAs consist of three
elements. The first, the memorandum itself, is relatively static.
The PM's watch list does not change very often, but significant changes in risk
and program support scope or direction should result in negotiation of a new
memorandum with the CMO and PMO endorsement. Both the personnel list and
the surveillance plan are more dynamic. Changes to these portions of the
MOA can be considered minor and are made with PM concurrence. The PI is
responsible for ensuring the MOA is current and accurately describes the level
of support provided to the PM. At a minimum, the PI must validate MOA
currency on an annual basis, and document the date of the last update field in
the PI module of E-tools.
1.2.3.
When a program managed contract has been awarded to multiple primes, such as in
a joint venture or teaming agreement, or is of such a scale that many CMOs have
to support it, a lead CMO must be identified. Determination of the lead
CMO must consider the contractual arrangement as well as the PMs
priorities. Upon designation of the lead CMO, the lead CMO PI
is responsible for coordinating the development of the overarching MOA with the
PM, and the PI/PSTs and Support Program Integrators (SPI/SPST) of the other
CMOs. In these cases, a separate annex to the MOA that is signed by the PM
and lead CMO Commander should be executed by the Commanders of the prime CMOs,
in order to clarify internal DCMA CMO roles and responsibilities. District
PI Directorates should assist in this process as necessary, particularly on the
large programs that cross district
boundaries.
2. Team
Management
2.1. Resourcing - CMO management should
strive to ensure that sufficient personnel with the expertise to execute the
program plan are appointed to the PST. During the annual performance
planning and budgeting cycle, program requirements have to be prioritized and
funded, and during the year adjustments should be made as changes occur.
The PI must coordinate with the CMO Commander to ensure the activities
outlined in the MOA are supported by the CMO's budget. 2.2.
Direct Access to Management - PIs should hold the grade or rank appropriate to
the program acquisition category designation in accordance with the Agency
standard position descriptions, and have direct access to CMO senior leadership.
Attendance at Management Council or Executive Steering Committee meetings allows
PIs to address acquisition strategy, process risk, resource issues, and
contractor required actions. Influencing contractor-required actions is a
critical component of Risk Handling.
2.3. Authority and Responsibility - The
PI and the Team Leader jointly determine the PST skill set requirements and
coordinate the identification of team members with CMO management. This
includes defining roles, establishing goals and priorities, and acting as a
coach to assigned team members. The PI should have the authority and
responsibility for resource commitment of PST members.
2.4. Training - PIs, including those
covered by dual-function position descriptions (where PI accounts for 51% or
more of job responsibilities), must be DAWIA certified in Program Management
(Level III for ACAT I and NASA Major Programs, and Level II for ACAT II & IIIs), as
well as being fully trained and Level II DAWIA certified in their respective
acquisition career field. ACAT I, II & III SPIs should be DAWIA certified at
Level II in Program Management. PST members, as a minimum, should be fully
trained and Level II DAWIA certified in their respective acquisition career
fields. In addition to DAWIA requirements, PIs and SPIs responsible for
programs with EVM reporting should complete EVM courses outlined in Section
6. PST member training requirements should be reflected in their
Individual Development Plans.
3.
Team Integration
3.1. Management Councils - Because of the
importance of having established a close management relationship between the
CMO, the supplier, and the Program Office, Management Council meetings are a
useful forum for addressing issues of mutual concern. PI involvement in
sharing process risk information and PST analytical outputs can drive supplier
corrective actions and have a positive impact on the desired outcomes of the PM.
3.2. Integrated Product Teams (IPT) -
Although PST members participate in activities such as Program Management
Reviews or Material Review Boards, and interact with their counterparts in both
supplier and Program Management organizations, they should also participate in
specific program IPTs. The PI should coordinate the efforts of PST
members assigned to working level IPTs.
4. Communication
Potential Changes to Criteria for Entry of Program in Program Integration
(PI) eTools Application (INFORMATION)
Enhancements to Program Integration
(PI) eTools Application (INFORMATION)
4.1. Real-Time Reporting -
Comprehensive, predictive, and timely information that we provide to the PM
should be considered a key function of a PI. The PI is responsible for
ensuring open, real-time communications with the PM. The PM often assigns
specific program office personnel to key subcontractors. In the interest
of promoting real-time, productive communications with the customer, SPIs should
establish regular communications links with their counterparts in the program
office. This ensures the timely exchange of information, analysis, and
recommendations between onsite SPST members overseeing critical subcontractors
and the program office. (Note: SPIs are required to provide the PI with
timely cost, schedule, and technical performance information and analysis so the
PI and PST members have a complete perspective on the program as a whole, and
the PI can communicate directly with the PM on a real-time basis. SPI
communication with program office personnel assigned to specific subcontractors
only enhances the DCMA/customer communication process). At the beginning
of a program, the PI should conduct a joint PST/contractor meeting. This allows
introduction of team members, an explanation of how the CMO will implement the
terms and conditions of the MOA, perform surveillance, and how identified
problems and issues will be resolved. It also provides the contractor an
opportunity to discuss potential program and contract cost, schedule, and
performance issues.
4.2.
Periodic Program Reporting -
The frequency and content of PI reports to the PM must be addressed in the
MOA. Periodic PI summary reports to the PM serve a number of
purposes, but are not a substitute for real-time communications. In
addition to capturing those issues addressed by the PM in the MOA, it provides
the PI an opportunity to summarize key program or process issues across the
broad spectrum of DCMA support activities and alert the PM to key issues or
concerns that are or may impact cost, schedule, and performance areas in the
coming weeks. As emphasized in the
PI/PST Process
Maturity Model, timely, forward-thinking communications with the PM and
Program Office personnel is a critically important aspect of the PST's support
to the PM. The report should not only address the prime contractor's key
performance areas, but also information, analyses, and recommendations from the
SPI and supporting PST members. Examples include changes in risk status,
information on contractor and subcontractor reorganizations, indirect rate
changes, or the status of forward pricing rate agreements. Program reports
should solicit customer feedback by referencing the survey website.
Customers can then complete a survey at
http://csat.dcma.mil/custsat/customer_sat/main.jsp
to help us better support their needs. The PI, SPI, and PST
Members should communicate on a regular basis with the PM, notwithstanding the
issuance of periodic written reports. In-plant presence provides DCMA
personnel with information and program perspective that the PM does not have,
given the separation of the Program Office from the prime contractor and key
sub-contractor locations. Timely communication with the PM and PM's staff
is an essential component of customer support. For Army
programs, periodic program reporting is accomplished through submission of DCMA
Assessments via the Army's web-based Acquisition Information Management (AIM)
System.
(Revised Army Program Reporting (INFORMATION))
4.3. Program Status
Charts (PSC) summarize the status of multiple prime contracts that contribute to
a single overarching program, and they
provide CMO Commanders, District and HQ staff a snapshot of program health.
They also provide perspective on key
program performance across each Service and at multiple locations of large
defense contractors. The PSCs are used
for a variety of purposes including: identifying
program trends, providing assistance to CMOs in assessing program issues,
preparing for meetings with Senior Customers (i.e.,
Service Acquisition Executives, Service Acquisition Staff and Program Executive
Officers), preparing for Defense Acquisition Executive Summary (DAES) reviews
and determining recent program status when attention is directed to a specific
program.
4.4. PIs
must prepare an internal DCMA PSC in the format shown at
Attachment
2 for each ACAT I, II & III program on a quarterly basis.
(Implementation of the Automated Program Status Chart eTools
Application (INFORMATION))
(Automated Program Status eTools Application (INFORMATION))
(Revised Army Program Reporting (INFORMATION))
This chart is
for internal DCMA use (Instructions
for preparation). The evaluation of each
category on the PSC is an independent DCMA evaluation developed by the Program
Support Team.
In order to mirror the DAES process, risk ratings will be
determined based on the same criteria as DAES. The DAES color code rating
system, which is explained in the Consolidated Acquisition Reporting System
(CARS) Users Guide, is at
Attachment 3.
The charts must
be sent electronically to the District PI Directorate for all ACAT I,
II, III and major NASA programs within five working days following the end of each
quarter. Districts must then submit the charts to HQ DCMA-PIM not later
than five working days later. All PSC Files must be clearly labeled with
the program name so it can be easily identified in electronic
transmissions. Occasionally, the Districts or HQ have a need for in-depth
program information with a focus on the level and quality of support DCMA is
providing. In addition to those data elements used to populate the
quarterly PSCs, PSTs should be prepared to capture those elements used in
preparing
periodic
program review charts for Senior Leadership Team briefs. Often, issues
arise concerning EVM data analysis. If the program is covered by EVM
requirements, the PST needs to be prepared to discuss its methods for developing
independent estimates at completion (IEAC), tracking and analyzing management
reserve (MR) usage, and variance root cause analysis.
4.5.
For Army programs, the monthly DCMA
Assessment input to AIM replaces the PSC submission. The DCMA Assessment
must include all pertinent PSC information, including contract and EVM data.
(Implementation of the Automated Program Status Chart eTools
Application (INFORMATION))
(Revised Army Program Reporting (INFORMATION))
4.6. Periodic Program Reviews occur at DCMA HQ.
DCMA-PIM recommends programs to the Director for review based on program risk.
A
Template provides instruction to assist in briefing preparation.
Two hours are allotted for program briefs. Due to time constraints, briefs are limited to the template
requirements, thus ensuring adequate time for discussion, questions, and
comments. The briefs may be delivered in person or via video
teleconference and provided by the CMO Commander or the PI. Cognizant CMOs
should deliver their briefing packages to their respective District
offices. The Districts should forward the packages to DCMA-PIM five
working days prior to the scheduled brief.
4.7. Customer Feedback - CMO senior
leadership, District, and HQ personnel communicate with the PM on a periodic
basis to assure that the PST is functioning well and providing support to the PMO, influencing positive outcomes.
5. Execution
5.1. Program Surveillance - Risk
Assessment Management Program (RAMP) is the primary tool to be used to develop
an integrated Risk Management Plan (RMP), and should be program specific unless
there are no unique processes or risks identified beyond the overall facility
plan. As leader of the PST, the PI must ensure that team member RMPs
adequately address contractor processes and process results that influence the
achievement of desired program outcomes identified in the MOA. Risk
Monitoring shall be conducted for all key processes. As a minimum, the PI
must establish a PST meeting schedule that allows the team to evaluate execution
of the plan and contract performance. Surveillance activities can then be
adjusted based on performance and assessed risk elements. High risk key
processes have a potential impact on readiness since failure to perform has a
negative impact on cost, schedule, and technical performance. The SPI's
role is the same as the PI, but at a subcontractor location. The frequency
and content of SPI reports must be addressed in the delegation.
5.2. Data Analysis - As the leader of
a PST, the PI is responsible for accumulating functional inputs into a
single, comprehensive analysis. PST members employ a variety of data
analysis tools in their program support efforts. The goal is to go beyond
mere journalistic reporting of program status to assessing what the various bits
of data mean to the health of the program, and ultimately to what the results of
the analyses imply regarding the future of the program. An integrated
approach to data analysis is necessary. For example, examination of earned
value data can provide a clear picture of what has happened in the past and,
assuming current trends remain constant , allow us to make reasoned predictions
of what will most likely happen in the future. This is the basis of the
Independent Estimate at Completion (IEAC), an estimate of ultimate program
cost. If we couple EV data analysis with critical path analysis within the
master schedule, we are not only able to predict how much the program will cost,
but how long it will take to complete. Root cause analysis assists in
determining why something happened, and allows us to make judgments regarding
the potential effectiveness of the contractor's proposed corrective
actions. Examination of Technical Performance Measures (TPM) trend lines
against glide paths through thresholds to goals can result in predictions on the
probability of success against technical challenges. Thus, we move from
reporting of information, through discussing what the information means - to
being able to state that, based on what we now know, this is what we think will
happen in the future (predictive analysis).
6. NASA Program Integration:
The following are additional, unique requirements for
supporting NASA delegations: PIs must be assigned to the major NASA
programs, including programs at the subcontractor level with direct delegations,
or re-delegations. In general, NASA programs should meet the ACAT
dollar thresholds contained in D0D 5002 to be considered major programs.
In addition, multi-functional delegations that require
support in four or more technical and/or business functions may be considered
as major NASA programs. A draft MOD should be submitted to the PM within 60 days
(or a mutually agreed upon timeframe) following the receipt of the
delegation.
|