Upon contract
receipt and review the Technical Specialist or their delegate
will assign the appropriate production
surveillance category (PSC) to the contract and make
appropriate adjustments in MOCAS/SICM. If an event
occurs that impacts contract risk, the PSC must be changed
in MOCAS/SICM to reflect the new risk level.
Delivery Schedule Manager (DSM) shall be used to communicate
actual and potential schedule delay notifications to the
customer and to respond to customer requests. If a customer
requests information or actions relating to Manufacturing and
Production using a method other than DSM, the CMT
will input the request into DSM and respond to the request via
DSM. (See Guidance paragraph 8.6 for waiver request
process)