Your browser doesn't support Javascript
DCMA Seal Defense Contract Management Agency (DCMA) Defense Contract Management Agency (DCMA)
Instructions Guidebook POCs COP
Process Tools & Additional Guidance Performance Successful Practices Pre-Process Information Training
 
Process
Flowchart
Guidebook
Consent to Subcontract/Contractor Purchasing System Review (CPSR)
Process - Process Description
 

TABLE OF CONTENTS

1.        INTRODUCTION
2.        RISK PLANNING

2.1 Consent to Subcontract
2.2 CPSR

 3.      RISK ASSESSMENT

3.1 Consent To Subcontract
3.2 CPSR

4.        RISK HANDLING

4.1 CPSR Schedule

4.1.1 Developing the CPSR Schedule


4.1.2 Reviewing and Coordinating the CPSR Schedule

            4.2 Obtain Data

                            4.2.1 Timeframes

                            4.2.2       Information Needed

                                            4.2.2.1    Data from the Contractor

                                            4.2.2.2    Data from Internal Sources

                                            4.2.2.3    Data from Other Government Sources

            4.3         Plan the Review

                            4.3.1       Review Data

                            4.3.2       Refine the Scope of the Review

                            4.3.3       Identify the Location(s)

                            4.3.4       Personnel

                            4.3.5       Funding

                            4.3.6       Administration

                            4.3.7       Security

            4.4          Arrange the On-Site Review

                            4.4.1       Time Line Tasks

                            4.4.2       Working Space

            4.5          Conduct CPSR

                            4.5.1       Conduct Pre-Review Meeting

                            4.5.2       Conduct Entrance Conference with Contractor

                            4.5.3       Review Policies, Procedures, and Forms

                            4.5.4       Review Sample of Purchase Orders and Subcontracts

                            4.5.5       Compile and Analyze Statistics

                            4.5.6       Interview Other Contractor Personnel

                            4.5.7       Final Review of Team Input

                            4.5.8       Write Preliminary Observations and Findings

                            4.5.9       Informal Exit with Contractors Purchasing Staff

                            4.5.10     Discuss Observations/Findings with the ACO             

                            4.5.11     Formal Exit Conference

                            4.5.12     Formal Letter

5.         RISK MONITORING

6.         RISK DOCUMENTATION

            6.1          Write Report and Recommendations

            6.2          Evaluate Corrective Action Plan

7.         Appendixes

            7.1        Appendix A          CPSR Risk Assessment Form

            7.2        Appendix B          Contractors Policies and Procedures Checklist

            7.3        Appendix C          Sample CPSR Recommendations

            7.4        Appendix D          CPSR Report

            7.5        Appendix E          Contractor Purchasing System Review Data from Contractor

 1.      INTRODUCTION

            1.1          The purpose of this Contractor Purchasing System Review (CPSR) guidebook is to provide assistance for personnel who may be required to perform a CPSR as well as providing background information for those personnel who use the information developed during a CPSR.

1.2                This guidebook provides the framework of the CPSR.  It does not provide the detailed procedures on how to perform a CPSR.  Please note that this guidebook is for reference only, is not directive in nature, and is not to be used as a substitute for the relevant Federal Acquisition Regulation (FAR) or Department of Defense (DoD) FAR Supplement (DFARS).  Those who are not directly involved in conducting CPSR's, including contractors, should find that the CPSR guidebook should help increase their understanding of the CPSR process.  The CPSR guidebook may be used as a training tool and as a desk reference.

2.      RISK PLANNING

2.1                Consent to Subcontract - The ACO, in consultation with the CMO operations team or functional specialists should review the contract and any modifications to understand the customer's needs and the requirements of the contract regarding subcontracts. 

                            2.1.1                                 2.1.1        Key processes are those which, if not properly controlled, can adversely affect contract performance, cost, or schedule.  Key processes should include:

                                            2.1.1.1    Advance Notification

                                            2.1.1.2    Request for ACO Consent

                            2.1.2       If the level of consent to subcontract is not considered appropriate the ACO should notify the PCO.

            2.2          CPSR - The ACO, in consultation with the CPSR Team, manages risk associated with contractor's purchasing systems.

                            2.2.1       A review is made per FAR 44.302(a) to determine if a contractor qualifies to have a CPSR performed.  The CPSR Team Leader should identify potential qualifying contractors for CPSR's.  The primary sources are contractors currently in the program, requests from contracting officers, requests from other DoD activities and requests from the CPSR Center.

                            2.2.2       When a contractor is qualified to undergo a CPSR, a risk assessment is conducted to determine the level of risk the contractor poses to the Government with regards to the contractor's management of their purchasing systems.  The cognizant ACO, in coordination with the CPSR Team Lead and Procuring Contracting Officers (PCOs), should determine which contractors require a CPSR.

                            2.2.3       The Contractor Risk Assessment form in Appendix A should be used to assess the contractor's risk level.  Based on the level of risk, the CPSR Center, in agreement with the cognizant ACO,  determines whether or not to schedule the contractor for a CPSR.

                            2.2.4       The CPSR Team Captain identifies the key processes and rationale that support the completion of a CPSR. Key processes are those which if not properly controlled, can adversely affect contract performance, cost, or schedule.

                                            2.2.4.1    Key processes should include:

                                                            2.2.4.1.1        Source Selection

                                                            2.2.4.1.2        Price/Cost Analysis & Negotiations,

                                                            2.2.4.1.3        Cost Accounting Standards,

                                                            2.2.4.1.4        Compliance to Public Law requirements, and

                                                           2.2.4.1.5        Contractors Terms and Conditions (review by DCMA Legal Counsel)            

                                            2.2.4.2    In addition, the following processes may be considered:

                                                           2.2.4.2.1        Contractor Vendor Rating Process,

                                                           2.2.4.2.2        Contractor Make/Buy Process, and

                                                           2.2.4.2.3        Contractor Internal Purchasing System Audit Process.

3.         RISK ASSESSMENT

            3.1          Consent to Subcontract - During the post award review the ACO should: (1) consider how new work affects the contractor's subcontracting process and other contracts currently in process in the contractor's facility; and (2) review the criteria in the contract to determine how many and which subcontracts need consent.  The ACO can then assess the risk presented.  If the level of consent to subcontract is not considered appropriate the ACO should notify the PCO.          

            3.2          CPSR - The considerations listed in FAR 44.202-2 for consent evaluation of particular subcontracts also should be used to evaluate the contractor's purchasing system.

                            3.2.1       Those contractors eligible for a CPSR should be given a risk assessment to determine if a CPSR is to be performed.

                            3.2.2       Risk, as used in this context, means the Government's financial, quality and delivery exposure posed by contractor operations. The first step in conducting a risk assessment is to collect certain data pertaining to the contractors purchasing system.  Each decision on each item should be documented in the file.  As listed in Appendix A, The Contractor Risk Assessment Form, the following factors have a bearing on the risk posed to the Government.

                                            3.2.2.1    Approval status history. For a contractor where a CPSR has not been performed, there is no approval status history. Where this data is available, review of it gives a good picture of the Governments risk. Does the contractor have a history of having an approved purchasing system or does its history show a record of bouncing back and forth between approved and disapproved? Clearly, a contractor with a history of a repeatedly approved purchasing system poses a smaller risk than the contractor with a history of approval being withheld.

                                            3.2.2.2    CPSR recommendations and repeat recommendations to the contractor.  For contractors whose purchasing systems have been reviewed before, the criticality of recommendations and repeat recommendations, when viewed over time, gives an indication as to the direction the contractor is moving with its purchasing system.  Decisions to perform a CPSR should be based on the significance of the recommendations.  Are they major or minor recommendations?  A trend pattern of major recommendations is an indication of high risk.  Minor recommendations that are not repeat recommendations may not pose much of a risk at all.  Consider the impact the failure to implement the recommendations has on the contractor's purchasing system.  Major recommendations pertain to compliance with public laws, and high cost practices and others as may be determined by the contracting officer.

                                            3.2.2.3    Dates of previous CPSRs and other reviews.  These dates let you know how long a contractor has been in the CPSR program and how frequently it has been subjected to CPSRs.  The longer the time spans between CPSRs, the greater the risk that the contractors purchasing system may have deteriorated.  What other reviews have been made of the contractors various systems?  The results of various internal purchasing system reviews, for example, can add to your risk assessment

                                            3.2.2.4    Government contract mix: cost-type, firm fixed price (FFP), etc.  A factor of risk is a type of contract or the mix of contract types that the contractor has.  Cost reimbursement contracts pose the most risk to the government whereas FFP contracts pose the least risk to the government.

                                            3.2.2.5    Direct material and material overhead as a percentage of total cost.  More material purchased for a contract implies greater cost to receive, store and handle that material.  A high material handling cost to material cost ratio is an indicator of higher risk.

                                            3.2.2.6    Sales to the Government as a percent of the contractors total sales.  It is generally thought that a contractor with sales to the Government as a relatively minor part of Its total sales poses a lesser risk than a contractor whose sales to the Government are a predominant portion of its total business.  This thought is base on the concept that the highly commercial contractor is more driven towards cost effectiveness and efficiency than are contractors whose business base is primarily sales to the Government.  However, a contractor whose sales to the Government are a relatively minor part of its total sales may become careless in performing to Government requirements.  Contractors selling commercial products tend to be driven by the competitive marketplace towards cost effectiveness and efficiency.  This may not apply, however, for contractors in sole source situations, and when the Government is a relatively minor part of their total sales.

                                            3.2.2.7    DCAA audit reports.  The DCAA performs "cost, systems, and functional reviews per the Contract Audit Manual (CAM).  DCMA uses portions and information from those reviews in order to determine the impact of risk associated with the contractors' purchasing systems.

                                            3.2.2.8    Input from the contracting officer and other members of the contracting officer's team.  The primary source of information about a contractor is the ACO.  The ACO is responsible for coordinating the efforts of all members (i.e., Quality, Industrial Specialist, Engineers, Pricing, Small Business, Property, etc.) of the field contract administration team and should be cognizant of the strengths and weaknesses of the contractor.

                                            3.2.2.9    Education, training, and experience of the contractor’s purchasing personnel.  A well trained procurement staff poses a smaller risk than an inexperienced, untrained staff.

                                            3.2.2.10 The contractor’s self assessment and internal auditing efforts.  Some contractors perform self assessments and internal audits of their purchasing activity.  A contractor who has an effective and aggressive self assessment and/or internal auditing program generally poses less risk to the Government.  Often the contractor shares the results of its internal audit programs with the Government.  The Contractor's data/results and self audit methods should be validated before being used.

                                            3.2.2.11 The contractor's relative position in Its Industry.  A determination should be made as to whether the contractor is the only source, or is one of many, in its relative position within that industry.  Generally, a sole source contractor poses the greatest risk.  Ultimately, competition drives the contractor to be cost conscious in order to improve its share of the market.  Industry leaders and well-established contractors generally pose a lesser risk.

                                            3.2.2.12 Reorganizations, mergers and divestitures.  Reorganizations, mergers, and divestitures can impact a contractor's purchasing performance, without regard to previous purchasing system status.  Changes resulting from these activities can be expected but are not necessarily predictable.  Purchasing personnel, policies, and procedures may be changed.  New people may be brought in.  Experienced people may be moved out or moved around.  Purchasing policies and procedures may be changed.

                                            3.2.2.13 Significant fluctuations in sales.  Large or unexpected fluctuations in sales, if not effectively managed may adversely affect the contractor's purchasing system.

                            3.2.3       Although the rating criteria shown on The Contractor Risk Assessment Form in Appendix A results in an objective numerical score, there is no established scoring system that provides the "right answer" when performing a risk assessment.  The evaluation of the collected data depends on the judgment of the CPSR specialist and that of the ACO.  There are times when the data discussed above is not available.  The Contractor Risk Assessment Form should be used, if possible, as a benchmark.

4.         RISK HANDLING

4.1          CPSR Schedule.  The CPSR Center Lead Analyst should develop a master schedule of CPSR Risk Assessments to be conducted during the next twelve months.   Copies of the master schedule are to be provided to the CPSR Center and Analysts, DCAA, HQ NASA, the cognizant ACOs and others as deemed necessary.  The Master CPSR schedule should be coordinated with the above to ensure that the schedule is prioritized and the duplication of effort is kept to a minimum 

                            4.1.1       Developing the CPSR Schedule. 

                                            4.1.1.1    The CPSR Center Lead Analyst develops a master annual schedule for conducting reviews.  Some factors to be considered in developing the schedule include the type of review, (i.e., initial, subsequent or follow-up); the date the contractor's approval was granted (if currently approved); whether PCOs are considering new awards, and other relevant factors (i.e., follow-up review tailored to specific ACO concerns, etc.)

                                            4.1.1.2    When a contractor has corporate wide/business unit wide purchasing procedures, consideration should be given to using established procedures (establishing procedures if needed) for a single review of corporate wide business unit wide procedures.  This corporate wide approach should be reviewed and approved by the CACO/DACO, coordinated with cognizant ACOs, affected CPSR Teams and affected CMO Commanders, and assigned to a Lead DCMA CPSR Analyst.  Results of the review should be shared with all cognizant CPSR Teams.  Any procedural recommendations made as a result of a review that affect corporate wide business unit written procedures should be addressed to the cognizant CACO/DACO and the CPSR Center.

                                            4.1.1.3    The CPSR Center Team Captain assigned determines the scope and duration of the reviews to be conducted and the resources needed in coordination with the Lead Analyst and/or Division Director.  The Team Captain should determine what other Government personnel may be required, and the role of contractor personnel assisting the audit. 

                                            4.1.1.4    When planning the schedule, the Lead Analyst should allow enough flexibility so that the schedule can be adjusted during the year.

                                            4.1.1.5    CPSR Teams should respond to requests for assistance from engineers and program managers who may need purchasing system status and information.

                            4.1.2       Reviewing and Coordinating the CPSR Schedule.

                                            4.1.2.1    CPSR teams and CMO personnel who perform CPSRs should coordinate their schedules to minimize disruption to contractor operations, and to ensure that no duplication of effort occurs.  Although the criteria and frequency of these reviews differs, successful coordination eliminates significant review preparation cost for contractors.

                                            4.1.2.2    Schedules should be shared among CPSR team members, cognizant ACO, Property, Transportation, Engineering, Legal Office, Small Business, Terminations, and NASA in coordinated reviews.  Where schedules do not match, copies of the most recent compliance reviews should be requested.  CPSR teams may negotiate with Small Disadvantaged Businesses (SADBU's) on what information to provide which might be helpful for them (degree of competition, outreach efforts) in determining a small business program rating.

                                            4.1.2.3    Schedules are to be shared and coordinated with DCAA.  Where schedule conflicts arise the CPSR Team Lead should revise the CPSR schedule to ensure maximum DCAA participation and to minimize the number of audit/reviews to a contractor.

                                            4.1.2.4    Funding issues should be decided early in the planning cycle.

                                            4.1.2.5    When the schedule has been reviewed and coordinated the contractors should be notified as to when the review is to be conducted.

            4.2          Obtain Data.  It is the responsibility of the CPSR Team Captain to make decisions on pertinent information required by the team per FAR 44.303 and FAR 44.202-2, in order to efficiently perform the CPSR.  The amount of data accumulated should maximize the team knowledge and minimize the time to digest it. 

                            4.2.1       Timeframes

                                            4.2.1.1    For reviews conducted for DCMDI (OCONUS) the requests for data should be forwarded to the ACO at least 90 days prior to the start of the review to allow for translation of the documents.

                                            4.2.1.2    For reviews in the CONUS the requests for data should be forwarded to the ACO 45 to 60 days prior to the start of the review.

                            4.2.2       Information Needed - Items on the list below are intended as memory joggers to Team Leaders and are neither all inclusive nor is all of the information needed for each CPSR.

                                            4.2.2.1    Data to be obtained from the Contractor.  (In addition to that required by FAR.  See also Appendix E.)

 

                                                            4.2.2.1.1                Copies of the contractors organization chart(s), showing the corporate management structure, down to at least the procurement department-head level.

                                                            4.2.2.1.2                Copies of the contractors procurement organization chart down to at least the first level of supervision. Either the chart itself or an accompanying table should show the number and job classification (or assignment) of personnel reporting to each first-level and higher tier supervisor.

                                                            4.2.2.1.3                Summary of Contractor sales and purchasing data.  (See Appendix E, Contractor Purchasing System Review)

                                                            4.2.2.1.4                List of major open contracts (prime and subcontract) as of a selected cut off date, broken out by project name or description, face value, and Unliquidated Obligation (ULO).

                                                            4.2.2.1.5                Copies of management reports such as shortage reports, weekly or monthly workload and work backlog reports, scrap/salvage reports, and repetitive reports to company management and/or the Government.

                                                            4.2.2.1.6                List of affiliates, autonomous or semiautonomous departments, and divisions indicating total amount of business awarded to each during current year.

                                                            4.2.2.1.7    Contractor self evaluations. Based on the specific review, the CPSR team leader should request contractor self evaluation of the following processes (usually requested in background data requests forwarded through ACOs prior to on-site visits).                      

                                                                            4.2.2.1.7.1             Standard purchasing and subcontract terms and conditions. Contractor legal counsel should review these clauses and certify that they are acceptable for use with the current FAR requirements. Contractor legal counsel should cite any changes that need to be made, and certify that the clauses are acceptable upon their revision. Some companies contract out for legal support, and certification from these attorneys is acceptable.

                                                                            4.2.2.1.7.2             Standardization program

                                                                            4.2.2.1.7.3             Value analysis/value engineering program

                                                                            4.2.2.1.7.4             Major subcontract administration

                                                                            4.2.2.1.7.5             Purchasing reports to higher management

                                                                            4.2.2.1.7.6             Purchasing cost saving reporting

                                                                            4.2.2.1.7.7             Supplier evaluation and rating methods

                                                                            4.2.2.1.7.8             Advance purchase planning

                                                                            4.2.2.1.7.9             Comparative sales and purchasing data

                                                                            4.2.2.1.7.10           Implementation of corrective action on previously identified deficiencies, and

                                                                            4.2.2.1.7.11           Any deterioration in the purchasing system since the last CPSR, and corrective action taken to date.

                                                            4.2.2.1.8  Metrics.  Many companies use health indicators and metrics to measure and report performance against predetermined tolerance levels.  Such indicators are acceptable means for contractors to demonstrate effective purchasing systems, and to justify the continuance of purchasing system approval.  They may not be used, however, to waive a risk assessment.  Contractors should take the lead in establishing and reporting their metrics to the local CMO.  CPSR teams should assist ACOs and these contractors to select the most important health indicators, and to evaluate the resulting metrics reports.  There should be a zero tolerance level for noncompliance with public laws.  ACOs should request CPSR teams to review any out of tolerance conditions to validate the contractor's findings and conclusions, and/or determine whether withdrawing purchasing system approval is warranted to protect the Government's interests. Some indicators for contractor metrics are:     

                                                                                4.2.2.1.8.1             Maximizing the incidence of competitive subcontracting (including price and other factors) 

                                                                                4.2.2.1.8.2             Justifying and documenting the need for legitimate single and sole source purchases                              

                                                                                4.2.2.1.8.3             Obtaining cost or pricing data and information other than cost or pricing data from prospective subcontractors and flowing down the correct FAR clauses to awardees

                                                                                4.2.2.1.8.4             Performing effective cost analyses of cost data

                                                                                4.2.2.1.8.4             Obtaining cost accounting standards disclosure statements or valid exemption forms, and flowing down correct FAR clauses

                                                                                                                                                                                            4.2.2.1.8.5             Performing effective price analyses of supplier quotations and proposals                                                                           

                                                                                                                                                                                            4.2.2.1.8.6             Performing effective negotiation with potential suppliers

                                                                                                                                                                                            4.2.2.1.8.7             Providing advance notification to the contracting officer of intent to subcontract, and obtain ACO consent prior to award           

                                                                                                                                                                                            4.2.2.1.8.8             Definitizing letter subcontracts within 180 days or before 40% of the work is completed                         

                                                                                                                                                                                           4.2.2.1.8.9             Maximizing on time supplier deliveries to protect prime contract schedules and  

                                                                                                                                                                                          4.2.2.1.8.10           Maintaining a satisfactory small business program rating.

 

                                                        4.2.2.1.9    Copies of contrac                                            4.2.2.2    Data to be obtained from Internal Sources.  The CPSR Team Captain should request copies of the most recent CMO QDR's, progress reports, and other pertinent documents.  Although CPSR reports may describe deficiencies from Quality Assurance CPSR reports, they should not duplicate recommendations already made.  Deficiencies wholly unrelated to the purchasing system should not be factors in the purchasing system approval decision.  Other sources of information include: Engineering, Production, Property, Small Business, Legal, and Transportation & Packaging from cognizant CMOs.  Any risk assessment or CPSR data should also be gathered.

                                            4.2.2.3    Data to be obtained form Other Government sources.  The CPSR Team Captain should determine the extent of data that is needed from other Government sources and send out the request letters at the same time as the letter requesting the data from the contractor.  Some sources of information are: DCAA, General Accounting Office (GAO), inspector General (IG), Defense Criminal Investigative Services (DCIS).

            4.3          Plan The Review - After the data is gathered the CPSR Team Captain, in conjunction with the customer, should refine the scope and the location (s) of the review and decide what assets are required.  Funding issues should be decided early in the planning cycle.

                            4.3.1       Review Data.  The CPSR Team Captain Is to review the data gathered and decide if it is adequate for the review.  If more information is required the Team Captain should request it.  When reviewing the collected data the CPSR Team Captain and ACO should consider the following:

                                    4.3.1.1    Contractor sales data including the number of subcontracts issued during the review period.

                                   4.3.1.2    Contractor's internal audits conducted prior to the scheduled review.

                                   4.3.1.3    Customer input from ACOs, PCO's, and other cognizant Government personnel

                                   4.3.1.4    Reports generated under CRAG or other applicable reviews.

                                   4.3.1.5    The last CPSR report.

                                   4.3.1.6    Any DCAA audits that impact the purchasing system that were conducted since the previous CPSR, or if this is an initial review, audits conducted during the previous 12 months.

                            4.3.2       Refine the Scope of the Review.

                                            4.3.2.1    In most cases, an initial review should constitute a complete appraisal of the contractor's purchasing system. Subsequent reviews may, if considered appropriate, constitute a complete appraisal of the contractor's purchasing system or be limited to those areas that the customer and the CPSR Team Captain determine necessary for adequate system analysis.  Some circumstances that should be considered when determining the extent of the review follow:

                                                            4.3.2.1.1    The past review resulted in withholding or withdrawing system approval.

                                                            4.3.2.1.2    A major change in the contractor's purchasing organization.

                                                                                                                4.3.2.1.3    The contractor has been awarded a prime contract involving system management responsibility.

                                                            4.3.2.1.4    The contractor has no contracts that require production deliveries.

                                            4.3.2.2    Any new responsibility that affects the contractor's purchasing organization and its coordination with other departments could be a situation where the ACO would want to be assured that the contractor's purchasing system is adequate for the purpose of dealing with the new responsibilities.

                                            4.3.2.3    When a complete appraisal is not required, the review should be limited to those areas that have been identified as an area of weakness or of special interest/importance.  For example, a GAO or IG report may indicate the need for a review limited to the particular area (s) under criticism, Similarly, if a deterioration in part of the contractor's system is discovered, such as in the performance of price/cost analysis or single/sole source justifications, only a review of those particular areas of the contractor's purchasing activities may be necessary.

                            4.3.3       Location - Identify the location to be included in the review.  If the contractor's purchasing system covers multiple locations, then the ACO and the CPSR Team Captain need to determine which locations to include in the review. 

                            4.3.4       Personnel.

                                            4.3.4.1    The Team Captain chooses the members of the team based upon the type of review, the length of on-site review time anticipated and the material/areas to be reviewed.  In order to utilize team member expertise in the most efficient manner and minimize disruption of contractor operations the CPSR Team Captain should give consideration to the background and skills of the team members.  A versatile team is able to take a broad view of the contractor's operations and appropriately distribute emphasis.  The roles of various potential team members are discussed below.

                                                            4.3.4.1.1    DCMA Technical Specialists: Technical specialists may be requested to contribute to CPSR's in their assigned areas, with no duplication of effort.  CPSR Team Captain should give any contractor self audit reports to the appropriate technical specialist for validation.

                                                            4.3.4.1.2    DCAA: When participating on CPSR teams, DCAA should be assigned the following topics:

                                                                               4.3.4.1.2.1             Material Estimating - DCAA auditors can extract information from existing Contractor Estimating System reports and flash audit records from individual prime contract proposal reviews.               

                                                                               4.3.4.1.2.2             Prompt payment discounts - Auditors usually know contractor accounting practices and their record keeping systems and techniques.

                                                                                                                                                                                          4.3.4.1.2.3             Interdivisional transfers - Contractors often purchase from other corporate segments.

                                                                                                                                                                                          4.3.4.1.2.4             Customers: The CPSR Team Captain should request, through the ACO, participation by buying office personnel.

                                                                                                                                                          4.3.4.1.2.5             Contractors:

                                                                                            4.3.4.1.2.5.1              Coordinated audits.  Team Captains should give consideration to inviting contractors to participate, either as run team members, or to some lesser degree, as seen fit by contractor management and the Team Captain.  To ensure objectivity, contractor participants should be internal audit personnel, or otherwise outside the materiel/purchasing span of control.  CPSR teams should not duplicate the efforts of its contractor team members, except as may be necessary to validate findings.  The degree of contractor participation should not be a factor in the ACO's decision to grant purchasing system approval.

                                                                                            4.3.4.1.2.5.2              Self Governance.  Contractors may increase their participation in CPSRs by volunteering to participate in self governance purchasing reviews.  This option is not appropriate for first time contractors because there would be no Government base line to use in the validation process.  Contractors may submit their self governance reports to their ACOs at any time.  When ACOs and CPSR team captains conduct the risk assessment, they should consider using the self governance report to determine the scope of validation necessary, the scope of the overall review, and the desired degree of contractor involvement in the next review.  (Note: Self Governance objectives by themselves do not constitute a set of standards or a checklist for determining whether reduced oversight is warranted.)

                            4.3.5       Funding:

                                            4.3.5.1    Funding, in general terms, should be discussed at the CMO level and determined in conjunction with developing the Annual and Quarterly CPSR schedules.

                                            4.3.5.2    Requests from DoD or NASA activities for CPSRs on contractors under DCMA cognizance that meet the criteria for a CPSR are to be provided at no cost to the recipient.

                                            4.3.5.3    Requests from DoD or NASA activities for CPSRs on contractors not under DCMA cognizance should be honored when manpower is available, with per diem and travel costs provided by the requesting activity.

                                            4.3.5.4    Requests from non-DoD Federal activities for CPSRs should be honored when assets are available, on a cost-reimbursable basis.

                                            4.3.5.5    Requests from non-Federal activities for CPSRs should be referred to the CPSR Center.

                            4.3.6       Overall Administration - The Team Captain serves as the overall administrative chief for the team, coordinating its efforts with those of the contract administration offices.  Responsibilities should include arranging meeting times and places, determining any special facilities needed and assuring the security of all the material made available to the team during the review.  The Team Captain may delegate any of these administrative duties as necessary.

                            4.3.7       Security

                                            4.3.7.1    Restricted access to a contractor’s facility may slow the progress of the CPSR team.  When required, it is recommended that the Team Captain arrange with the contractor to have non-escort badges available to the CPSR team members from the first day of the on-site review.  Any Government property (e.g., laptop computers) brought into the contractor's facility may require registration with the contractor’s security office.  The Team Captain should inquire about this, and restrictions on removing audit records from the plant, before starting the on-site review.

                                            4.3.7.2    When planning a review in a foreign country, it is necessary to request and obtain country clearance.  The required procedures are somewhat unique to each country.  Guidelines are published in the DoD Foreign Clearance Guide, DoD 4500.64G.  Country clearance usually serves as security clearance to enter the contractor’s facility allowing the team members access to relevant production plants as well as administrative offices.  It is not always required, but it is recommended that CPSR analysts frequently traveling abroad on business obtain a Government passport.

            4.4          Arrange the On-site Review - After the scope of the CPSR has been determined, planning the actual effort begins.  The following sections provide a general guide to the extent and type of planning activities required.

                           4.4.1           Time Line Task.

4.                                                        4.4.1.1      Initial/In-depth CPSR

                                                           4.4.1.1.1    6-8 weeks prior to scheduled review contact ACO and team members to reconfirm review dates, arrange logistics.   

                                                           4.4.1.1.2    4-6 weeks prior to scheduled review mail request for data to the contractor and the other Government specialists.  Request copy of policy and procedure manual from contractor 4-6 weeks prior to review.

                                                           4.4.1.1.3    2-4 weeks prior to scheduled review the Team Captain receives list of purchase orders and selects sample.  Review Policy and Procedure manual and inform contractor of missing or inadequate areas.     

                                                          4.4.1.1.4    1 week prior to scheduled review the Team Captain reviews all data received on-site visit from the contractor and the Government specialists and prepares entrance conference notes and arranges meetings as necessary. It may be necessary for the Team Captain to conduct meetings with ACO, DCAA, and/or DCMA Technical Specialists prior to the start of the on-site review in order to resolve outstanding issues and discuss recommendations offered by other Team members.

                                           4.4.1.2      Other than Initial/In-depth Reviews

                                                            4.4.1.2.1    2-4 weeks prior to scheduled on-site visit the Team Leader determines which steps are required to accomplish the review

                                                            4.4.1.2.2     1 week prior to on-site visit the Team Leader selects sample, if necessary, and prepares entrance conference notes.

                            4.4.2       Adequate Working Space – A room adjacent to, or close by, the purchasing department should be provided to serve as the team's on-site location.  Normally contractors provide CPSR teams with hard copy purchase order folders that it used in its own internal approval cycle, supplemented with working folders if they are requested.  Therefore, the team's working room should contain enough tables or desks to seat all the members and to permit them to spread out the folders to be reviewed.  The room should be large enough to hold interviews of contractor personnel.  It should be adequate for writing draft report paragraphs covering their respective topic areas.  The extent of the contractor’s participation in the review should be described.                                       

            4.5          Conduct the CPSR

                            4.5.1       Conduct Pre-Review Meeting (Government Personnel Only)

                                            4.5.1.1    On the first day of the on-site visit, the Team Captain should hold a meeting with all the members of the team.  At this meeting, the Team Leader should state the plan for the review.  If not done earlier, the Team Leader should announce the assignments of the team members and define their responsibilities.

                                            4.5.1.2    Government personnel should be invited to share with the team any purchasing system related reviews and audits, such as operations audits, property system surveys, MMAS audits, etc., which may have been conducted during the previous 12 months.  This may enable the team to forego duplicative effort.

                                            4.5.1.2    The ACO should be requested to describe briefly the contractor's major programs, where the work is performed, whether there is significant research and development work, and the contractor's general attitude toward the impending review.  The ACO should inform the team of specific topic areas of concern.  This meeting should establish the entrance conference attendees and the spokesperson for the Government on the various aspects of the review.  The Memorandums of Agreement between DCMDI and the CONUS CPSR Districts should be reviewed in detail before meeting the overseas contractors.

                            4.5.2       Conduct Entrance Conference with Contractor - The Team Captain should open the conference by introducing the Government attendees, beginning with the ACO, etc., down the chain of command.  If the contractor personnel in attendance are not familiar with CPSRs, the team leader should explain the CPSR process, function and the benefits accruing to both the Government and industry.  At all conferences, the Team Captain should explain the extent of the review to be undertaken, the purchasing system sub-processes most important to gaining system approval, and the timing of events.  Inform the contractor that only the ACO will give official directions and make the final approval/withholding approval decision in accordance with FAR Part 44.305-1.  The contractor may agree to provide a briefing on their purchasing system at the entrance conference.

                            4.5.3       Review Policies, Procedures and Forms - The team's first task is to review the contractor's policies, procedures, and forms in order to know how the purchasing system should operate.  (Appendix B)

                            4.5.4       Review Sample of Purchase Orders and Subcontracts.      

                                            4.5.4.1    Once the team has familiarized itself with the policies, procedures and forms, the team should analyze the selected sample of purchase order folders drawn from the contractor’s files.  The team normally reviews the purchase orders using CPSR software.  If one or more members of the team use the hard copy form, the data may be computed manually and entered into CPSR software upon return to the duty station.  The CPSR model software may be shared with outside agency personnel to use during joint audits or when they participate in CPSRs. Purchase/subcontract orders awarded by the contractor exclusively in support of Government contracts awarded to the contractor using competitively awarded firm fixed price and fixed price with economic price adjustment procedures, or that are for commercial item contracts pursuant to FAR Part 12, will be excluded from review in accordance with FAR Part 44.303.

                                            4.5.4.2    For contractors who have "paperless" systems and/or keep records in an automated storage system, CPSR personnel should access the records in the medium used by company personnel.  The team should also determine the integrity of the contractor's methods for authenticating internal approval signatures and vendor certifications in automated systems.  Unless FAR or the contracting officer require originals, CPSR teams should consider as acceptable, vendor certifications, proposals, etc., in facsimile form.

                                            4.5.4.3    The Team Captain, in consultation with the contractor's liaison, determines whether to ask questions as they come up in the purchase order review, or to save them to ask several at one time.  Any apparent deficiencies should be verified through interviews with the buyers or liaison personnel before final judgment.  If deficiencies relate to contract clause compliance, the team should check the contractor's copy of the prime contract to verify applicability.

                                            4.5.4.4    Team members should conduct their interviews in an objective manner, inviting contractor personnel to be frank and forthcoming with information.  In many cases, CPSR teams educate new buyers by virtue of their questions/explanations of Government policy.  Care should be taken; however, not to direct contractor personnel to take specific actions which may incur constructive change problems for the customer.  Team members should not criticize company management or discuss possible legal violations (e.g., acceptance of subcontractor kickbacks) in the presence of contractor personnel.

                                            4.5.4.5    CPSR teams should custom tailor the sample size of purchase orders and subcontracts where contractors conduct their own internal audits, including CRAG Part 5, or some other type teaming arrangement.  CPSR teams should sample purchase orders reviewed by the contractor, and a percentage of purchase orders not included in the contractor's sample.  This provides confidence that the contractor's sample is representative of the universe.

                            4.5.5       Compile and Analyze Statistics

                                            4.5.5.1    The CPSR Software Model program automatically sorts and prints spreadsheets detailing the data gathered from the sample purchase orders.  It also compiles statistics and prints statistical summaries.  If the Software Model Program is not available this should be done manually.

                                            4.5.5.2    Each member of the team should examine the statistical summaries and share their opinions on what trends appear to exist, and what directions to take for the rest of the review.  Negative indicators occurring early in the year need not automatically result in a recommendation.  Procedures may have already been corrected. Purchase lead time and delivery statistics deserve particular attention.  For example, 30 days lead time may not necessarily be too short for some products, and 90 days is definitely not enough for long lead items.

                                            4.5.5.3    Verify the facts concerning any apparent public law violations

                                                            4.5.5.3.1    Cost or Pricing Data requires obtaining one or more cost data submissions upon which prime and subcontractor negotiations were based, and a certificate that the most recent cost data was accurate, current, and complete.  The certificate is required by FAR 15.406-2(a).

                                                            4.5.5.3.2    Cost Accounting Standards requires obtaining disclosure statements or exemption certificates from subcontractors and flowing down the applicable CAS clauses in qualifying subcontracts.  Notifying the ACO is required by FAR 52.230­6 (e)(3).

                                                            4.5.5.3.3    Notifying contracting officers before awarding subcontracts under cost plus fixed fee prime contracts is a legal requirement (notifying contracting officers of pending awards under other types of prime contracts, and obtaining ACO consent in all cases, are regulatory requirements, not legal ones).

                                                            4.5.5.3.4    Contractors failing to definitize their letter subcontracts before 40% of the work is accomplished (or within 180 days - whichever comes first) is a violation of FAR 16.603-2(c)(3).

                                         4.5.5.4    Any violation of Public Law may constitute a major system deficiency.  The Team analyzes the causes and considers all the circumstances of each situation to arrive at a recommendation which is in the best interests of the Government. In most situations, negative statistical indicators provide a basis for further inquiry, and should not be used alone to justify recommendations for corrective action.

                                            4.5.5.5    When comparing CPSR team statistics to those submitted by contractor internal audit, team members should determine whether the results are similar enough to support the contractor's conclusions. If the results are dissimilar, the team should attempt to discover a reason for the finding through discussions with the contractor liaison, and/or select an additional sample of purchase orders and subcontracts on which to base further analysis.

                            4.5.6       Interview other Contractor Personnel.

                                            4.5.6.1    Interview other contractor personnel on issues resulting from the analysis of statistics and also on areas not covered in the sample.  During the sampling of purchase order process, the team may have questions concerning some of the files that were reviewed.  This does not necessarily mean that the files are deficient, but it does mean that further explanation or clarification is needed.  Typically the questions are answered by the cognizant buyer or senior purchasing/subcontracting management.  The response may be oral or written depending on the complexity of the question and the response.  There may also be occasions where the team interviews personnel from outside of the purchasing organization regarding questions that are not under the control of the purchasing personnel.  For example, there may be a question regarding the requisitioning process.

                                            4.5.6.2    Interviews may be conducted with personnel outside the purchasing area covering topics that may be included in the CPSR report but are not directly discussed in the sampling process.  The following cover some of the areas to be addressed: standardization, value analysis, make-or-buy and ethics.

                            4.5.7       Team input Final Review - Prior to the conclusion of the on-site portion of the CPSR, the team reviews the input from all members, including DCAA, Legal, and other DCMA Technical Specialists to decide if there are any areas where further investigation is needed.  The Team Leader is responsible for coordinating resolution.

                            4.5.8       Write Preliminary Observations and Findings - Once all on site activities have been completed; it is time to assess the results of the reviews.  The Team Captain should write preliminary observations and findings that provide the basis for the exit conference discussion and formal CPSR report.  The team considers the results of the sampling, and the team members' input.  After the statistics have been reviewed, along with all of the other information generated during the review, the Team Leader decides if any problems found are serious enough to warrant presenting formal recommendations to the contractor requiring corrective actions.  It should be recognized that there may be situations where isolated non-systemic problems are found.  While a formal recommendation may not be warranted, the problem should be addressed in the exit conference and discussed in the CPSR report to preclude recurrence.

                            4.5.9       Informal Exit with Contractor's Purchasing Staff - It is recommended that an informal exit meeting with the contractor's purchasing personnel be held.  This meeting provides the purchasing personnel with advance warning concerning the issues that wilt be discussed at the exit conference.  It provides the purchasing staff with the opportunity to provide additional information or evidence that could have an effect on the review team's findings.

                            4.5.10     Discuss observations/findings with the ACO - The ACO should be kept apprised of the progress of the review.  There are at least three areas to be discussed with the ACO.  The first is to confirm the ACO's attendance at the exit conference.  Secondly, and most Important, the review team should go over the results of the review and discuss the proposed recommendations.  Depending on the desires of the ACO, an in-depth presentation may be required or a brief summary may suffice.  The Team Captain and the ACO have an understanding of the formal recommendations.  Finally, the ground rules for the exit conference should be discussed.  It is preferable that the ACO letter transmitting the findings and recommendations be signed at the conclusion of these discussions.  In the event that the ACO is unable to attend the exit conference, the Team Captain still needs to brief the ACO as explained above.  However, in addition, to this, he/she should explain that an informal list of findings may be presented to the contractor at the exit conference.  This document lists the recommendations, and alerts the contractor that the ACO's formal letter with recommendations is forthcoming.

                            4.5.11     Formal Exit Conference - The review team should hold an exit conference with the contractor's top management to ensure that they are aware of any serious problems that may have been uncovered.  It is not necessary that the exit conference be held on the last day of the review.  It is recommended that the Commander of the CMO or their representative be invited to attend the exit conference.  The Team Captain should provide positive observations as well as negative comments.  The letter with recommendations for improvement of the purchasing system is given to the top contractor official in attendance.  The Team Captain explains the basis for the recommendations, reviews the statistics resulting from the sampling process, gives the overall results of the review, and highlights that the contractor is to respond to the ACO within 15 days of the ACO's formal letter.  (It can be assumed that the contractor purchasing management  briefs their upper management on the review results, so an in-depth explanation of every facet of the review should not be necessary.)  The Team Captain should provide responses to unanswered questions as soon as practical.

                        4.5.12.    The ACO's Formal Letter - The ACO's letter with recommendations shall request that the contractor respond within 15 days with its corrective action plan to the ACO, copy to the Team Captain in accordance with FAR Part 44.305-2(c).           

           5.1                 RISK MONITORING

                            5.1.1       The CPSR identifies major and minor problems with the contractor's purchasing system.  These problems may reduce the effectiveness and efficiency of the purchasing system and increases the risk level to the Government.

                            5.1.2       The Corrective Action Plan describes actions the contractor proposes to take to correct the problems identified in the CPSR.  The ACO in consultation with the CPSR Team should review the Corrective Action Plan to determine the appropriateness of the proposed corrective actions.  The contractors purchasing system should be monitored to ensure the corrective actions are accomplished and the actions actually correct the problems.  Failure to implement Corrective Action Plan changes should be considered as evidence that the risk level for that contractor may need to be re-evaluated.

            6.1         RISK DOCUMENTATION

                            6.1.1       Write Report and Recommendations

                                            6.1.1.1    The report should be concise and reflect conditions as found; and should identify the contractor, processes reviewed and recommended corrective action(s) (Appendix C).  Evidence of CPSR Team Captains review of the final report, work papers, and other pertinent documents should be held in the official CPSR file.

                                            6.1.1.2    The CPSR Report format is shown at Appendix D.  The following exception apply:  When contractors have submitted internal audit reports on a portion of their purchasing system to the Government, the CPSR team has the option of attaching copies of those reports to the summary, and include a paragraph stating the Team's validation method and results.  The summary should not duplicate topics included in these internal audit reports.

                            6.1.2       Evaluate Corrective Action Plan - The ACO shall request the contractor to provide the Corrective Action Plan within 15 days after the exit conference, with a copy to the CPSR Team Captain in accordance with FAR Part 44.305-2(c)..  The CPSR Team Captain evaluates the Corrective Action Plan for responsiveness to the recommendations, appropriateness of corrective actions, and capability of meeting the designated milestones.  Unacceptable Corrective Action Plans are to be returned via the ACO to the contractor for reconsideration and rework.  The Corrective Action Plan and the Team Captain’s evaluation of the CAP should be made part of the final CPSR report..    

                            6.1.3       On the first page of the report, (Appendix D), the Team Captain should inform the ACO of his/her recommendation to approve or withhold approval of the purchasing system.  The ACO should not issue approval or withhold approval prior to obtaining a copy of the final CPSR report.    

                            6.1.4        The Team Captain should provide a copy of the final report to the ACO and DCAA.   

revised 16 Apr 08

 
page last updated on
cm:ron.odaniell@dcma.mil