Contract Closeout Guidebook

Defense Contract Management Agency

6350 Walker Lane, Suite 200

Alexandria, VA 22310


June 2009


TABLE OF CONTENTS

 

                                                                                                Page

Contract Closeout Time Standards                                  3  

 

Basic Contract Closeout                                                4

 

Fixed Priced Contract Closeout                                      6

 

Cost Type Contract Closeout                                         14

 

Time and Material/Labor Hour Contract Closeout            21

 

Incentive Contracts                                                      21

 

Quick Closeout                                                             22

 

Early Closeout for IDIQ Contracts                                   29

 

Reconciliations and Section Four                                    33

 

MOCAS Maintenance of BOAs and BASICS                         36

 

Reopened Contracts in MOCAS                                       36

 

Other                                                                         37

 

Solutions for Problem Closures                                      41

 

Summary                                                                    52

 

Appendix A - R2 Delay Reason Codes                             53

 

Appendix B - Acronym List                                           55

 

Appendix C  - References                                             57

 

Appendix D - Attachments                                           58

 

 

CONTRACT CLOSEOUT GUIDEBOOK

                                     

 

This guidebook provides instructions for correctly closing contracts.  Users are encouraged to submit recommendations for improvements to the Defense Contract Management Agency (DCMA):

 

    Defense Contract Management Agency

    ATTN: Contract Closeout Performance Advocate

    6350 Walker Lane

    Alexandria, Virginia 22310    

 

Closing cost contracts can be more difficult than closing other contracts and require coordination among the administrative, procurement, and payment offices.  When closeout is accomplished properly, the administration, payment, and official contract files should close around the same time. 

 

                                                                   

 

Back To TOC


CONTRACT CLOSEOUT STANDARDS TIMEFRAMES

 

 

 

The standard timeframes for closing physically complete contracts are located in the Federal Acquisition Regulation (FAR) 4.804.  A contract is considered physically complete when the contractor has completed performance and the Government has inspected and accepted the supplies and services.   Furthermore, all optional provisions, if any, must have expired.  Firm Fixed Price contracts should be closed not later than 6 months after the physical completion date.  Cost Reimbursement, Time and Material (T&M) and Labor Hour (LH) contracts require settlement of indirect cost rates and should be closed not later than 36 months after the physical completion date.  All other contract types should be closed not later than 20 months after the physical completion date. 

 

 

Standard Closeout Timeframes

(FAR 4.804)

Timeframes

MOCAS Codes and Contract Types

6 Months

J  FIRM FIXED PRICE

36 Months

L  FIXED PRICE INCENTIVE

R  COST-PLUS AWARD FEE

S  COST CONTRACT

T  COST SHARING

U COST-PLUS-FIXED-FEE

V COST PLUS INCENTIVE FEE

Y TIME AND MATERIALS

Z  LABOR HOUR

20 Months

A  FIXED PRICE REDETERMINATION

K  FIXED PRICE W/ECONOMIC PRICE ADJUSTMENT

O  OTHER – BASIC ORDERING AGREEMENT/BLANKET

    PURCHASE AGREEMENT (BOA/BPA)

 

 

 

 OVERAGE CONTRACT CODING

 

    DCMA ACOs are required to assign Delay Reason codes and input Estimated Completion Dates (ECD) for MOCAS Part A Section 2 overage contracts.  As a result PKX notifications of delays in closing are transmitted to the POC.  The ACO is required to assign an "Office of Primary Responsibility" (OPR) code in the R9 remark MOCAS Field when entering Delay overage reason codes F, H, M, P, V, or W.  The OPR numeric codes are used to designate who has the primary responsibility to complete the coded closeout action: 71 - Services, 72 - Contractor, 73 - DCMA, 74 - DCAA, and 75 - DFAS.  See appendix A for a complete listing of the R2 overage reason and OPR codes.  ACOs are encouraged to place additional closeout comments in the ACO notebook.  DFAS is responsible for automatic closeout of Part B contracts from CAR Section 2 following final payment.

 

 

Back To TOC

 



BASIC CONTRACT CLOSEOUT

 

 

The contract closeout process starts at contract receipt and review and proceeds throughout the life of the contract.  MOCAS input data must accurately represent the contract in order to ensure proper management, payment, and closeout.  When all contract requirements have been met and the contract is physically complete, it should be moved to MOCAS Section 2.  The easiest contracts to close are short term Firm Fixed Price contracts with one Accounting Classification Reference Number (ACRN) for each Contract Line Item Number (CLIN) and no special provisions.  Cost-Type contracts with multiple ACRNs for each CLIN and special payment provisions are the most difficult to close. 

 

Many closeout problems increase in difficulty over time.  The inability to locate transaction support documents and to read faded print in hard copies of documents are two recurring problems.  Furthermore, if funds cancel before closure, appropriation law limits the types of adjustments that can be used to correct lines of accounting payment errors.  Also, it can be difficult identifying and locating the responsible contracting officer because of reorganizations and closures directed by the Base Realignment and Closures Commission.  In addition, over the past 20 years thousands of companies have gone out of business or been purchased by larger companies.  Novation agreements may or may not have been signed by the gaining company.  These activities have contributed to the difficulty in closing old contracts.   

 

What You Can Do To Simplify Closeout

 

 

 

Check for Payment Instructions

 

ACOs are reminded to review contract payment instructions to determine compliance with DFARS Procedures, Guidance and Information (PGI) 204.7108 Payment instructions. 

 

 

 

 

 

What Contractors Should Do To Simplify Closeout

 

 

 

Physical Completion

 

Once the contract is physically complete and moved to section 2, MOCAS will transmit a Contract Completion Statement (interim PK9/EDI 567) to the contracting office.   The completion statement will automatically be sent to the buying activity to provide notice of physical completion.  The contract should be closed within the FAR standard timeframe.  However, it should not be closed if the contract is in litigation, under appeal, or pending termination (Ref. FAR 4.804-1(c)).  These contracts should be assigned the appropriate dormancy code and moved to MOCAS section 3.  Once contracts have been entered into section 3, they should be reviewed periodically to update their status.  A contract, for example, was originally moved to section 3 awaiting review by the Armed Services Board of Contract Appeals.  When the appeal was denied, the contractor filed for bankruptcy.  Accordingly, the Dormancy Reason Code should be updated from BCA to BKRPT.  In addition, if the closeout date is expected to exceed the overage date, an estimated closeout date must be entered into MOCAS and revised as necessary.

  

 

Section 3 Dormant  Reason  Codes

CODE           

EXPLANATION

BCA

Armed Services Board of Contract Appeals (ASBCA) Case

TERM-C    

Termination for Convenience

PL

Public Law-Claim Pending (e.g., PL 85-804)

BKRPT

Bankruptcy

CIL

Contractor in Litigation

CLL 

Under Investigation

GUA

Contract containing provisions for extended testing periods after shipment and before final notice of acceptance from an estimation where final payment is withheld from contractor

LLD

Labor Law Determination

VE

Contingent Value Engineering Payment

DEBT

Deferred DEBT - Request for Debt DEFERRAL has been approved by the Finance Officer

NOTES: 

  • R3 Reason Code DEBT must be used in Conjunction with R9 - 64,  Deferred Debt  
  • TERM-D  (Termination for Default) is not a valid section 3 code

 

 

 

 

Now the actual closeout can occur 

 

If all contract terms and condition were met, then follow FAR 4.804-5, procedures for closing the contract.  The administrative contracting office must review the contract funds status and notify the contracting office of excess funds available for deobligation.  Next, follow the checklist of closeout administrative actions below that must be accomplished when applicable to the contract.

 

 

Once all applicable actions are completed, the contracting officer processes the Final Payment NLA in MOCAS or E-Tools.  MOCAS transmits a contract completion statement (PK9/EDI 567) to the contracting office.   If for some reason the contract is not in MOCAS, the ACO will prepare a contract completion statement on DD Form 1594. 

 

 

Closed-Contract Database (CCDB)

 

The Closed-Contract Database (CCDB) system was activated on December 4, 2000 and acts as a repository of MOCAS  contracts closed after the date.  It stores contract data on an optical storage device that may be viewed on line for ten years after the contract has closed (DLAM 8000.3  MOCAS Users Manual For Contract Administration), Chapter 11 contains instructions for using the CCDB.

 

 

Back To TOC


FIRM FIXED PRICED (FFP) CONTRACT CLOSEOUT

 

 


Difficulties closing fixed price contracts are usually associated with documentation of deliverables and unliquidated obligation balances.  Contracts will remain in CAR section 1 until both of the following conditions have been met:

 

 

The final shipment document should alert the Industrial Specialists or Procurement Technician to input production history which generates a “Production Complete” remark on the R8 Remarks field within MOCAS.  The contract should automatically move to section 2 after the final acceptance information has been processed.  The movement of a contract into section 2 causes several things to happen. 

 

 

 

 

 

Problems with FFP Contracts Moving to CAR Section 2

 

If Firm Fixed Price contracts do not automatically moving to section 2, the following checks are suggested:

 

 

 

 

FPP Contracts Awaiting Final Acceptance

 

Obtaining destination final acceptance documents is DFAS' responsibility.  However, when final acceptance documents are not received by the contract management office (CMO) Terminal or payment office, the ACO can then request a statement of final acceptance from the customer and annotate the ACO notebook. 

 

Data items on a Contract Data Requirements List (DD Form 1423) that do not require a DD Form 250/Receiving Report are usually consolidated into a single ‘dummy’ service line item in MOCAS.  A DCMA Notice of Completion can be utilized to signify completion of this item.  See DCMA Integrity of MOCAS Delivery Performance Data Document for information on how to process a Notice of Completion.

 

The ACO reviews the contract file to ensure that all modifications have been entered into MOCAS.  DFAS, Receiving Activity, Buying Activity and Contractor may be able to provide copies of missing acceptance documents.   In all cases, if no final DD Form 250/Receiving Report is available, the contractor history will be input using “PROD001” as the shipment number.

 

The ACO should inform DFAS of actions taken by DCMA personnel to manually move contracts into CAR Section 2.  This is usually accomplished by entering remarks into the ACO Notebook.    

 

 

FFP Contracts After Movement to CAR Section 2

 

Movement of a contract into section 2 will prompt the ACO to perform several actions. The completion of the Contract Closeout Check List (DD Form 1597) is necessary to ensure all closeout administrative requirements are completed on other than firm fixed price type contracts and firm fixed price contracts with special closeout requirements.  The DD 1597 is optional for all other contracts.  

 

Closeout Checklist

 

 

 

 

 

 

 

 

 

 

 

 

 

 

All Deliveries Accepted on FFP Contracts

 

The ACO ensures that all contract items such as hardware, data, software, spares, and support equipment have been delivered and accepted by the government before the contract is closed.

 

 

Identify and Remove Excess Funds on FFP Contracts

 

FAR 4.804-5 states that once a CMO receives evidence of physical completion, they will review the contract funds status and notify the PCO of any excess funds available for deobligation at the outset of the closeout process.  It is recommended that this notification be done by e-mail with a return receipt to confirm notification.  When excess or negative unliquidated funds exist, a funds review should be performed at the accounting classification reference number (ACRN) level to determine the cause.

 

 

 

Final shipment and acceptance of the product/service on firm fixed price contracts entitles the contractor to receive final payment.  Cost and Fixed Price Incentive (FPI) contracts require settlement of final overhead rates and incentives.  In some cases, obligated funds are no longer required because of quantity variance.  Excess funds may exist on maintenance and repair contracts where the repairs cost less than originally estimated.  Because ACO settlement of overhead rates with DoD contractors can be a lengthy process, it is important to review contracts to identify and remove excess funds at the time of physical completion.  Working with the contractor, the ACO should estimate the total government monetary liability under the contract.  Historically, funds have generally not been declared excess until after settlement of indirect rates; however, the contracting officer should accomplish an initial funds review within 30 days of contract completion.   The PCO or ACO should issue a deobligation modification to remove excess funds as early as possible.  It is equally important to avoid deobligating funds that may be required for final payment.  

 

The .01 ULO has often been used to identify cancelled funds prior to the alpha cancelled funds indicator.  Send DCMA Form 1797 to DFAS to request adjustment of the "penny down" and to close the contract.  

 

 

All Actions Definitzed

 

Occasionally, urgent or unusual circumstances necessitate authorizing a contractor to start work before the contract has been negotiated.  The contract authorizing such effort must include a NOT-TO-EXCEED (NTE) or ceiling price and a schedule for definitization.  Prior to contract close-out, the ACO and PCO must work together to ensure that all actions under the contract have been definized.  

 

 

Subcontracts Closed

 

The prime contractor must go through procedures with its subcontractors who are similar to those used by the government.  The ACO must ensure that all of the prime's subcontracts have been paid and closed before the prime contract can be eligible for contract close-out.

 

 

Disposition of Government Property

 

Government property provided to the contractor during contract performance and not consumed must be dispositioned at the end of the contract.  Any property acquired or manufactured by the contractor, but is excess to the contract at completion, may also become government property under certain conditions.  This property also must be dispositioned before the contract can be closed out.  The FAR provides procedures for the proper disposition of government property, which include contractor reporting of all government property.  The government will review the report and provide specific instructions to ship, leave in place, or scrap the property.

 

If the contract contains property clauses, a DD 1593, Contract Administration Completion Record, is automatically generated by MOCAS when the contract becomes physically complete and can be retrieved by the CMO through REVEAL.  When the property has been cleared the property administrator inputs the disposition into the DCMA Property Administration Data System and an R9 code “55” will appear in MOCAS.  If the Code 55 is missing, a DD 1593 should be submitted to the Property Administrator for review and clearance.  The contract will not close unless the Code 55 remark is indicated.

 

 

Disposition of Classified Material

 

All classified documents must be dispositioned in accordance with government security regulations and accounted for by the contractor.  This can be accomplished when a final DD Form 254, DoD Contract Security Classification Specification, is issued, indicating disposition, or the contractor provides written certification that all data has been properly processed.  (See DODD 5220.22-M, National Industrial Security Program Operating Manual about disposition and retention).  Be sure the prime contractor has cleared all subcontracting DD 254s. 

 

Upon physical completion of a contract, a copy of the DD Form 1593, marked "Information Copy" is sent to cognizant Industrial Security Office. The cognizant Industrial Security Office can be found on the contract DD 254.  The ACO does not need confirmation or certification of completed actions from the security office to proceed with closeout.

 

 

 

Final Patent Report

 

If the contract contains a patent rights clause, FAR 52.227-11 or 13, a final patent report must be submitted by the contractor, preferably on a DD Form 882, Report of Inventions and Subcontracts, within 3 months after physical completion of the contract.  It must list all patent claims made under the contract or certify that there were no inventions and list all subcontracts which include a patents rights clause or certify that no subcontracts were issued with this requirement.   If the contract contains FAR 52.227-11, Patent Rights -- Ownership by the Contractor, a final patent report is required only if there is an invention.  If DFARS 252.227-7039, Patents--Reporting of Subject Inventions, is also in the contract a final report is required within two (2) months after completion of the contracted work.   The PCO should forward the clearance request and patent report to the cognizant patent counsel for clearance. 

 

Negative DD 882s

If the final patent report is negative, the ACO may include language in their letter to the PCO "if the PCO fails to issue a response within 60 days, patent clearance will be deemed to have been issued."  The following is required:

 

 

It is important to note that pursuant to FAR 227-12(n)(3), the Government has a 3-year look-back period after final payment on the contract to examine the books and records of the contractor for the purpose of asserting title and/or determining ownership rights to patentable subject inventions if the final patent report is found unacceptable.  The contractor has a regulatory duty to retain its books and records for 3 years after final payment on the contract.  As such, if in the unlikely event an unreported invention is discovered after closure, the contract can be reopened and the invention issues addressed.

 

Other than Negative DD 882s

If the DD 882 contains a report of patentable subject inventions or if the ACO has reason to believe that a negative DD 882 has failed to disclose an invention, the ACO should not impose a 60-day suspense for a patent clearance response.  

 

Final Royalties Report

 

If the contract contains a refund of royalties’ clause, FAR 52.227-9, a final royalty report must be submitted by the contractor stating the royalties paid or required to be paid.  This report must be submitted before final contract payment

 

 

Value Engineering Change Proposals

 

If the contract includes FAR 52.248-1, verify no outstanding Value Engineering Change Proposals (VECPs) requiring payment or disposition exist before closing contract.

 

 

Terminations/Claims/Disputes

 

All open actions and liabilities must be resolved prior to closeout.  The government may at any time during contract performance fully or partially terminate contracts for default or for convenience.  The government may terminate a contract for default when the contractor has materially breached the contract by failing to perform in accordance with contract requirements.   Under termination for default, the contractor is liable for any additional costs to the government to obtain terminated items.  The government may also terminate a contract for convenience.  Termination for convenience can occur when Congress or the program office withholds funding or the user determines that the item is no longer required.  Pursuant to the Termination for Convenience clause the government is liable for certain costs. 

 

A contractor at any time has a right to submit a claim against the government for a perceived government liability which at the time is not recognized in the contract.  An example of such a claim is when the contractor submits a proposal because it asserts that a government individual by his actions required the contractor to accomplish effort not specified in the contract.

 

If a claim is denied by the government or the government and the contractor cannot agree on certain other contract issues, the Disputes clause of the contractor the right to submit its dispute to a third party such as the Armed Services Board of Contracts Appeal (ASBCA) for resolution.  Alternate Dispute Resolution is another means available to both parties.

 

 

Litigation Resolved

 

The contractor, under the Disputes Clause, may appeal a decision of the contracting officer directly to the Court of Federal Claims.  Also, the prime contractor may sue or be sued by a subcontractor for damages related to the contract in question.  The ACO and PCO must work together to ensure that any litigation and resulting cost impact is resolved under the contract before the contract is closed.

 

 

Warranty

 

The FAR contains a number of warranty clauses suitable for use in different acquisition situations. Some of the warranty clauses can extend well beyond the physical completion of the contract.  As long as there is not a CLIN or money attached for extended warranty, the contract should not be held open just for warranty.  The contractor should have a process on how to handle a warranty item and if necessary; the contract can always be reopened through the CCDB.  Just because a contract is closed in MOCAS does not relieve the contractor of his contractual responsibility to perform under the warranty clause.  Contract containing provisions for extended testing periods after shipment and before final notice of acceptance where final payment is withheld from contractor should be moved to MOCAS section 3 and coded “GUA”. 

 

 

Excess vs. Remaining Funds

 

After contracts are physically complete and ready to be closed, except for funds, there may be instances where unliquidated funding remains on the contract.  In these instances a review must be accomplished to determine if the funds are “excess” or “remaining” to the contract requirements.  Upon completion of the review, the circumstances that cause the funds balance will dictate whether funds must be deobligated via modification because they were “excess” or Q final-ed because they are remaining funds.

 

Excess funds are funds relating to a specific line item or deliverable that was not performed on a contract.  A contract modification must be issued to deobligate excess funds.  Some examples of contracts that have excess funds follow: 

 

 

Remaining funds” are funds left on contract due to price variance, rounding or cost underrun and where all contract performance as required by the contract has been completed and paid in full.  The ACO Notebook will be annotated with a remark that the $XX (Amount of Funds) funds are remaining funds.  Some examples of contracts that have “remaining funds” follow:

         

 

 

Movement to CAR Section 5

 

Once all required closeout actions have been completed, the ACO should take the following actions to move the contract out of MOCAS and provide closeout notification to the buying activity.  MOCAS will generate a notice of last action (NLA) when final payment has been processed for Part A contracts.  Verify that a Final Pay NLA has been issued.  (Reminder: If MOCAS does not contain final payment information on the CCN screen (final voucher number and final payment date), the ACO should create a G NLA, which will populate those fields and allow a final pay FNLA to process.  Once the Final Pay NLA remark is entered on the R7 line of the MOCAS data record, the ACO can proceed with closeout in accordance with MOCAS Manual, DLAM 8000.3, chapter 4, Section 2.4.5.  On the following workday, the ACO should verify that the contract actually moved to Section 5.)  MOCAS will automatically generate a PK9/EDI 567, Contract Completion Statement, in lieu of a DD Form 1594, which notifies the buying activity that the contract is closed.

 


 

FIXED PRICE CLOSEOUT CHECKLIST

 

Action

Completed

Date

Final Acceptance Received?

 

 

Final Acceptance Entered in MOCAS?

 

 

LISSR Data Balanced (Line Items)?

 

 

PSCN Data Entered ("Production Complete" in R8 Remarks field )?

 

 

Contract Moved to Section 2?

 

 

ULO Balance Equal $0.00

 

 

PCO Notified of Excess Funds?

 

 

ACO Deobligated Excess Funds with Modification?

 

 

WIP ULO Balance Equal $0.00? (Progress Payment ULO)

 

 

Has Government Property Been Cleared? (55 Code)

 

 

Has Industrial Security Office Been Notified, for classified contracts?

 

 

Final Royalty Report Received from Contractor?

 

 

Final Royalty Report Clearance Received from PCO?

 

 

Final Report of Inventions (DD882) Received from Contractor?

 

 

Final Report of Inventions Clearance Received from PCO?

 

 

Final Pay NLA or DD1593 Issued?

 

 

Final NLA or DD1593 Signed and Processed by ACO?

 

 

Contract Moved to Section 5?

 

 

Non-MOCAS Contracts - DD1594 Completed for Contract File?

 

 

 

 

 

Closing DLA Other Disbursing Office (ODO) Contracts

 

When DCMA entered into the agreement to administer contracts paid out of SAMMS for DLA, a Class Deviation was issued which relieved the ACO from the FAR/DFARS requirement to track final payment and perform an excess funds review/recommendation on these contracts.  DLA ODOs close automatically if they are in MOCAS Part A and coded correctly.

 

Criteria for DLA ODO Auto Closeout:

 

*If the ACO wants to prevent automatic closeout of a DLA ODO contract, enter code 56 in the R9 remarks field.  Code 56 will cause the contract to be bypassed by the automatic closeout process.  The ACO must manually close the contract by entering a G and F NLA to close these contracts.

 

 

Closing Non DLA Other Disbursing Office (ODO) Contracts

 

For Other Disbursing Office (ODO) contracts, with the exception of DLA ODOs verification should be made with the payment office that final payment has been made and that the ULO balance equals zero. 

 

Criteria for NonDLA ODO:

 

Back To TOC


 


COST TYPE CONTRACT CLOSEOUT

 

 

Cost type contracts are the most complex contracts to administer and close.  Their final price is based mostly on a negotiated settlement of allowable and allocable cost that may not be decided for several years after physical completion.  There are several initiatives in place such as Real Time Rates and Quick Closeout (further detail provided below) that can minimize the impact that delays in settling indirect cost rates often have on closeout.  However, to prevent closeout problems, the contractor and contract should be monitored.

 

 

Monitoring Cost-Reimbursable Contracts

 

Contractor areas that should be monitored include:

 

 

 

 

 

 

 

 

 

It is helpful when individual contracts are monitored in the following areas:

 

 

 

 

 

 

 

 

 

 

By monitoring contractor and individual contract status, the problems associated with the closeout process, including final reconciliation of funds, will be minimal.

 

 

Movement to Section 2 – Physical Completion Cost Contracts

 

Cost type contracts will remain in section 1 until completion of contract performance.  Upon evidence of contract completion (receipt of final acceptance document or PCO statement), the Industrial Specialist or Procurement Technician will input the production history and balance the Line Item Schedule and Shipment Record (LISSR).   

 

After final acceptance, if the contract does not automatically move to section 2, then the ACO shall request that the Trusted Agent move the contract to section 2, which causes several things to happen:

 

 

 

Awaiting Final Acceptance for Cost Contracts

 

Contracts with destination acceptance requirements may hold up movement to section 2.  Obtaining this acceptance is a DFAS responsibility.  Destination final acceptance documents are often delayed or not received at all by the payment office or contract management office.  The ACO can, however, request a statement of final acceptance from the customer and once received, should annotate the ACO Notebook and request that the Trusted Agent move the contract to section 2. 

 

Data items on Contract Data Requirements List (DD Form 1423) that do not require a DD Form 250/Receiving Report are consolidated into a single ‘dummy’ service line item in MOCAS.  A DCMA Notice of Completion may be utilized to signify completion of this item.  See DCMA Integrity of MOCAS Delivery Performance Data Document for information on how to process the DCMA Notice of Completion.

 

After Movement to CAR Section 2

 

Movement of a contract into section 2 will prompt the ACO to perform several actions described below.

 

Closeout Checklist

 

The completion of the DLA Form 1597 should be used as a tool for ensuring all necessary steps in the closeout process are completed on other than firm-fixed-price type contracts and firm-fixed-price contracts with special closeout actions.  The DLA 1597 is optional for all other contracts.  It is a good idea to begin filling out a checklist when a contract moves into section 2. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

These actions are explained in Firm Fixed Price Section of the Guidebook.

 

  

Work with DCAA on Final Indirect Rates for Cost Contracts

 

Determination of final overhead rates is dependent on a review of the contractor’s incurred direct and indirect costs.  FAR 52.216-7 and FAR 52.216-13 requires the contractor to submit a final indirect cost proposal to the Government within 180 days of the close of its fiscal year.  

 

DCAA is responsible for auditing the yearly submission of the contractor's final overhead cost proposals and providing a formal report of its findings to the ACO.  The agency is responsible for ensuring that all proposed overhead costs are consistent with both the Cost Accounting Standards (CAS), if applicable, and the cost principles in FAR Part 31.  The "Allowable Cost and Payment" clause, FAR 52.216-7, provides for reimbursement of costs incurred in contract performance that are deemed "allowable" by the contracting officer, in accordance with procurement regulations and contract terms.  In establishing the allowable indirect costs under a contract, indirect cost rates are applied to the allowable contract base cost.  Indirect cost rates are generally accumulated into logical cost groupings to permit distribution of expenses in relation to benefits received by the cost objectives.  One such example of these indirect costs pools is manufacturing overhead, which represents costs incurred by the company that cannot be directly attributed to the contract (such as management salaries, buildings and maintenance).  The ACO must determine whether or not all overhead rates that apply to a contract have been negotiated.  The contractor is not eligible to submit a final voucher until all the applicable indirect costs and overhead rates have been negotiated or established.

 

Contractor Submission of Final Voucher

 

Once final annual indirect cost rates are settled for all years of a physically complete contract, the contractor must submit a completion invoice or voucher reflecting the settled amounts and rates within 120 days, unless an extension has been approved in writing by the contracting officer.  To determine whether a period longer than 120 days is appropriate, the contracting officer should consider whether there are extenuating circumstances as listed in FAR 42.705 (b) (1) through (5).  If the contractor fails to submit a completion invoice or voucher within the specified time period, the contracting officer may:

 

 

 

FAR 42.705 explicitly states the right of the contracting officer to unilaterally determine the final contract payment amount when the contractor does not submit the final invoice or voucher within the time specified in the contract. The contracting officer determination must be issued as a final decision in accordance with FAR 33.211.

 

 

DCAA Audit of Final Voucher and Cumulative Allowable Cost Worksheet (CACWS)

 

A CACWS summarizes total cumulative allowable costs for all open flexibly priced contracts.  (see Cumulative Allowable Cost Worksheet).  ACO should encourage contractors to submit a CACWS with their annual indirect cost rate proposal for audit by DCAA and update it within a reasonable time after rate settlement.  The Contractor's ability to track cumulative allowable cost by contract is essential for an adequate billing system and necessary to ensure that cumulative amounts billed do not exceed total estimated contract cost ceilings.

 

The CACWS is designed to expedite contract closeout by eliminating the need for DCAA to audit the final voucher and prepare a separate contract audit closing statement.  This saves time and resources for both the contractor and government.  The ACO can ensure that the total payment amount stated in the CACWS equals the total amount requested for each contract as stated in the final voucher payment support documentation.  However, if the ACO cannot determine the cumulative allowable costs by contract using the CACWS, or if there are subcontractor costs, he should request that DCAA audit the final voucher.

 

 

Credit Final Vouchers

 

Credit Vouchers cannot be submitted electronically.  In the past, an ACO would receive a contractor refund check attached to a final voucher reflecting a credit amount.  However, by the time all government parties processed the voucher and check, the date of the refund checks was over 6 months old.  The National City Bank Corporation received these checks from DFAS.  Their policy prohibited accepting non-Treasury checks older than six months unless the check explicitly specified a longer period.  These checks were known as "stale dated checks."

 

To eliminate the above circumstances, and to comply with the government's paperless goals, the Automated Cash Collection System (http://www.pay.gov/)  was created.  ACCS provides the ability for contractors to submit refunds/payments to DFAS electronically.  When contracts are ready to close and contractors are required to submit a refund/payment to the Government, they are encouraged to use ACCS to process a credit interim voucher.  After the refund/payment posts to the contract, then the contractor should submit a zero-final voucher to the ACO for review/approval.

 

 

Excess vs. Remaining Funds

 

After contracts are physically complete and ready to be closed, except for funds, there may be instances where money remains on the contract.  In these instances a review must be accomplished to determine if the funds are “excess” or “remaining” to the contract requirements.  Upon completion of the review, the circumstances that cause the funds balance will dictate whether funds must be deobligated by modification because they were excess or Q final-ed because they are “remaining” funds.  An explanation of the difference between Excess and Remaining funds can be found under the FFP contract closeout.

 

 

Final Voucher Review/Approval

 

ACO review/approval of a final voucher should include:

 

 

 

 

 

 

 

 

 

 

Personnel involved in the final payment process should be aware of the significant differences in the appointment qualifications and responsibilities for a certifying officer and a contracting officer.

Considering these differences, it is important that ACOs exercise care when approving final/completion vouchers  

 

 

Closeout of Cost Contracts

 

Upon processing and payment of the final voucher by DFAS, the contract should move to section 5.  If payment is made and the contract does not close, the ACO should first verify that all prior vouchers have been paid and the payment was coded as a final payment (type 1 code) in the disbursement history.  If this is the case, then the ACO can request their trusted agent to generate a G NLA to be processed by the ACO.  If the payment is coded as a type 2 and there are remaining funds, the ACO should annotate the notebook and process a G and F NLA or E-Tools closeout application.

 

 

Contract Completion Statement

 

The ACO is required to report final payment and completion of all administrative actions to the buying activity on DD 1594.  When contracts close in MOCAS, the system will generate a MILSCAP Format PK9/EDI 567 Notice which is used in lieu of the DD 1594.

 

If a contract is closed with a ULO balance, MOCAS will automatically generate a Q Final transaction to reduce the ULO to zero.  As a result of the Q Final transaction, a “CLR Obligation Auto-Adjustments Resulting From CNN Action” list is generated.  DFAS reviews the list to determine which contracts shall be reopened and/or adjusted for financial reconciliation.

 

DFAS will automatically reopen those contracts where reconciliation is necessary.  The contract may reopen in section 1 or section 4.  If ACO assistance is necessary, DFAS will contact the ACO directly.

 

 

Canceled Funds (Replacement Funds Required)

 

If adequate funding is still on the contract but has since canceled, the ACO will submit the final voucher to DFAS for payment.  The voucher will reject for insufficient funds and DFAS will code it “DFAS Merged Account (DMACT)” in the invoicing screen of MOCAS.  After verification, DFAS will request replacement funding from the funding activity.

 

ACOs should monitor final vouchers that require replacement funds ensuring that the invoice is coded as “DMACT” and included on the current DMACT list posted to the DCMA Canceling Funds page.  Partial payments can occur against the final voucher possibly resulting in premature closeout.

 

Back To TOC


TIME AND MATERIAL/LABOR HOUR CLOSEOUT

 

 

Where early closeout is not applicable, the closeout procedure is identical to the cost-reimbursable closeout procedure.  If an audit is required, DCAA will review material costs and labor hours expended to make sure that the charges are consistent with the contract. 

 

Upon receipt of a contract audit completion statement, the ACO should proceed with closeout.

 

Note:  These contracts will close automatically in MOCAS based on the presence of a payment coded as a type 1 final payment and R9 Remarks code 55 to indicate that all property actions are complete if a government property clause is in the contract.

 

 

Back To TOC

 


 


INCENTIVE FEE CONTRACT CLOSEOUT

 

 

Incentive type contracts are still subject to submission and negotiation of the cost elements that will be used in the formula for the incentive arrangement. 

 

Final Settlement Proposal Submitted

 

If the contract is an incentive contract and all overhead rates applicable to the contract have been negotiated, the contractor is eligible to submit its repricing settlement proposal.  The provisions of the incentive arrangement incorporated in the contract provide a formula procedure to determine the amount of profit the contractor has earned and this formula is not renegotiated.  However, cost elements used in incentive formulas, or cost type CLINs, are subject to this final settlement proposal.  The final repricing proposal would include all outstanding cost issues including such items as unsettled claims and undefinitized contract modifications.

 

 

DCAA Audit and PCO Negotiates Settlement

 

Based on DCAA and ACO input, the PCO negotiates the final settlement proposal, and then normally processes a contract modification adding or subtracting funds. The negotiating of final settlement proposal may be delegated by the PCO to the ACO.

 

 

Completion Statement and Final Voucher Submitted

 

After either receipt of the final modification adding or reducing funds for an incentive contract, the contractor submits its voucher (SF 1034) or commercial invoice for the final payment.  The final voucher/invoice is part of the "contract completion package," which includes the release of claims and other required documents.  The release of claims is a signed dated statement from the contractor, substantially the same as the following:

 

 "Release of Claims, Contract No. _______, (Program Name), Pursuant to the terms of the above contract, the government of the United States, its officers, agents, and employees are hereby released and discharged from all liabilities, demands, obligations, and claims arising under or by virtue of said contract."

 

 

Back To TOC

 


QUICK CLOSEOUT

 

 

Background

 

The quick closeout process offers an alternative to holding contracts open until indirect cost rates are settled.  When it becomes apparent that there will be a delay in the settlement of final indirect rates, it is recommended that the ACO utilize quick closeout where applicable. 

 

Use of quick close-out procedures should be the first area looked at when deciding how to close a contract.  Frequently current billing rates are used as the quick close-out rates.  Because these rates are established by the contractor and reviewed by DCAA and the ACO, they are considered credible and can be used to invoice and close the contract at a relatively small cost.

 

 

FAR Regulation

 

The procedure is identified in FAR 42.708.  Specifically, quick closeout procedures may be used if:

 

·        The contract is physically complete.

 

·        The amount of unsettled indirect cost to be allocated to the contract is relatively insignificant.  Indirect cost amount are insignificant when:

 

o       The total unsettled indirect cost to be allocated to any one contract does not exceed $1,000,000.00.

o       Unless otherwise provided in agency procedures, the cumulative unsettled indirect cost to be allocated to one or more contracts in a single fiscal year do not exceed 15% of the estimated total unsettled indirect costs allocable to cost-type contracts for that fiscal year.  The contracting officer may waive the 15% restriction based upon risk assessment that considers contractor’s accounting, estimating and purchasing systems; other concerns of the cognizant contract auditors, and any other pertinent information.

 

·        Agreement can be reached on a reasonable estimate of allocable dollars.

 

 

Quick Closeout Not a Binding Precedent

 

Unlike early closeout procedures, the determinations of final indirect costs under quick closeout procedures are final for the contracts it covers and no adjustments are made to other contracts for over or under recoveries of costs allocated or allocable to the contracts covered by the advance agreement.  Additionally, indirect cost rates used in the quick closeout of a contract are not considered a binding precedent when establishing the final indirect cost rates for other contracts.

 

 

Identifying Quick Closeout Candidates

 

The ACO should maintain close coordination between DCAA and the contractor in determining quick closeout candidates.  The candidates can be identified in various ways:

 

·        ACO – The ACO usually is the primary person who can identify candidates for quick closeout.  The ACO should consider the volume of contracts awaiting settlement of indirect rates and that will be affected by canceling funds.  Quick closeout is an excellent way to close contracts and preclude millions of dollars from canceling.  Another area that ACOs may consider is time and material type contracts.  These contracts are ideal for quick closeout because the only redeterminable amount is usually the general and administrative (G&A) costs associated with the other direct costs (ODCs) in the contract.

 

·       DCAA – Sometimes the auditor will contact the ACO and recommend particular contracts for quick closeout.  Often times the auditor is approached by a contractor regarding quick closeout.  When these recommendations are received, the ACO should review the contracts and any other contracts for that particular fiscal year and determine if quick closeout procedures are practicable.

 

·        PCO – A PCO will sometimes contact an ACO concerning closeout status of a particular contract and will often inquire about quick closeout possibilities. 

 

·        Contractor – The contractor will occasionally request quick closeout procedures for a given contract or group of contracts.

 

 

Negotiating Quick Closeout Rates

 

Once the quick closeout candidates are identified, the ACO should coordinate with the contractor and DCAA before beginning the negotiation of quick closeout rates.

 

 

 

 

 

 

 

 

 

XYZ COMPANY

INDIRECT COST RATE HISTORY

 

   LAST 3 SETTLED YEARS                    PROPOSED CERT. RATE              FINAL RATE

 

FY 00

      

Overhead                                  123.22%                                     122.10%

 

G&A                                          10.00%                                      9.50%

 

FY 01

      

Overhead                                  124.51%                                     122.50%

 

G&A                                          10.50%                                      10.00%

 

FY 02

      

Overhead                                  125.00%                                     123.59%

 

G&A                                          12.00%                                      10.00%

 

Unsettled Year

      

FY 03

      

Overhead                                  125.79%   

 

G&A                                          12.57%

 

   

ACO Analysis of the above

 

The contractor has proposed using FY 03 certified rates for quick-closeout of contracts completed in their fiscal year 02 (fiscal year 03 rates have not been determined by DCAA).  In looking at this history, it is clear that contractor proposed rates were higher than the final determined rates in the past three years.  If the ACO should use the contractor proposed FY 03 rates for use in quick-closeout, it is likely that the Government will be overcharged.  Since the last three years proposed rates were higher than the audited rates, it is likely that FY 03 proposed rates are higher than what the final determined rates will be.  The ACO should consider decrementing the proposed FY 03 rates using the following options.

 

 

The ACO has two options for determining a rate decrement

 

 

 

 

When using the decrement factor method, the ACO would   

 

Calculate the difference between the proposed/certified rates and the settled rates for the last three years, which will be the basis for the decrement factor.

 

Calculate the average decrement factor

 

Apply the average decrement factor to the unsettled rate to determine the proposed final rate.

 

     Fiscal Year       Proposed     Audited         Factor                  Formula

 

2000             15.23%          15.57%          -.0223           (15.23 - 15.57) / 15.23

 

2001             22.00%          21.85%            .0068          (22.00 - 21.85) / 22.00

 

2002             22.30%          19.86%            .1094          (22.30 - 19.86) / 22.30

 

2003             18.41%                            

Factor Sum:    .0939          (.0223) + .0068 + .1094

 

              Average:   .0939 / 3 =   .0313

 

Decrement Factor:    18.41 x 3.13 = .57

 

Proposed Rate:         18.41 - .57 = 17.84

 

          Fiscal year 2003:  G&A:  18.41 - .57 = 17.84%

 

 

 

When using the decrement percentage method, the results are as follows:

 

     Fiscal Year       Proposed     Audited        Factor            Formula

 

2000             15.23%          15.57%          102.23%        (15.57 / 15.23)

 

2001             22.00%          21.85%          99.32%          (21.85 / 22.00)

 

2002             22.30%          19.86%          89.06%          (19.86 / 22.30)

 

2003             18.41%         

                                      Factor Sum: 290.61%        (102.23 + 99.32 + 89.06)

 

                                                     Average:  290.61 / 3 = 96.87

 

                                      Decrement Factor: 18.41% X 96.87% = 17.83%

 

                                       Proposed Rate:     17.83%

 

          Fiscal year 2003:  18.41% x 96.87% = 17.83%

 

 

 

 

 

o       estimated rates for the final fiscal year of contract performance based on the contractor's actual data adjusted for any historical disallowance found in prior years' certified final incurred cost proposals.

 

 

 

 

Preparing an Advance Agreement

 

Once an agreement is reached for the final rate, the ACO should prepare an advance agreement.  Both the contractor and the ACO should sign the agreement.  A sample Advance Agreement follows:

 

QUICK CLOSEOUT AGREEMENT with XYZ COMPANY

 

1.  This agreement is entered into by and between the Defense Contract Management Agency [name of office], a Department of Defense activity and XYZ COMPANY organized and existing under the laws of [State], having offices in [City].

 

2.  This agreement is entered into under the authority of Federal Acquisition (FAR) 42.708, “Quick-Closeout Procedure” and FAR 52.232-7 “Payments under Time-and-Materials and Labor-Hour Contracts” and/or FAR 52.216.7 “Allowable Cost and Payment.”

 

3.  The purpose of this agreement is to set forth indirect cost rates for fiscal year 2002 to be assessed against: “other direct costs” only, which are included in contracts priced on a time and material basis (unless otherwise specified in the contracts) and/or appropriate direct costs only, which are included in contracts priced on a cost plus fixed fee basis (unless otherwise specified in the contracts).

 

These contracts will be closed prior to the establishment of indirect cost rates for fiscal year 2003.  The subsequent audit of and the establishment of final indirect cost rates for this year will have no affect on the final price and closure of these contracts.  There will be no adjustments made to other contracts for over or under recoveries of costs allocated to the contracts covered by this agreement.  These indirect cost rates are hereby established for applicable to Government contracts as listed in ATTACHMENT A only.

 

FISCAL YEAR:  2003                

 

OVERHEAD RATE:  124.28%

 

G&A RATE:  11.57%

 

Establishment of these rates shall not be considered a binding precedent when establishing the final indirect cost rates for other contracts.

 

4.  Upon full execution of this agreement, XYZ Company will perform audits of the affected contracts and reconcile all applicable accounts using the indirect cost rates established herein.  Once this is accomplished, or within thirty (30) days after full execution of this agreement, whichever is sooner, XYZ Company will submit to the Administrative Contracting Officer, a final voucher for each of the affected contracts.

 

5.  It is understood and agreed that the affected contracts are physically complete.  It is also understood and agreed that the amount of redeterminable indirect costs associated with any one of the affected contracts is less than $1,000,000.00 and the total amount of determinable indirect costs to be allocated to the affected contracts in 2002 is less than 15% of the total redeterminable indirect in that year.

 

6.  Notwithstanding the provisions of paragraph 3, 4 and 5 above, this agreement shall not change any monetary ceiling, contract obligation or specific allowance or disallowance established by the terms and conditions of the affected contracts.

 

IN WITNESS WHEREOF, each of the parties hereto has caused this Agreement to be executed by its duly authorized representative.

 

DEFENSE CONTRACT MANAGEMENT AGENCY                       XYZ COMPANY

 

[OFFICE NAME]

 

DEPARTMENT OF DEFENSE

 

BY:  _____________________________         BY:  __________________________

 

TITLE:  ___________________________        TITLE:  ________________________

 

DATE:  ___________________________        DATE:  _________________________

 

Important:  If Quick Closeout Rates are established based on the DCMA Deviation, paragraph 5 of the agreement will need to be revised.

 

 

DCMA Class Deviation (Quick Closeout Rates)

 

This deviation authorizes Administrative Contracting Officers (ACOs) to close specific contracts prior to the establishment of final indirect cost rates regardless of dollar value or the percent of unsettled indirect costs allocable.  This deviation may be used provided the contractor has submitted a final certified indirect cost rate proposal which is audited by the Defense Contract Audit Agency (DCAA).  This deviation is subject to the following conditions:

 

 

 

 

 

 

 

 

Submission of Final Vouchers for Quick Closeout

 

As stated in the Advance Agreement, the contractor will have 30 days after execution of the advance agreement to submit a final voucher on the affected contracts.  The final voucher should be provided to DCAA for final audit.  The Defense Contract Audit Manual (DCAAM) paragraph 10.903 “Quick Closeout Procedure Reports” indicates that:

 

 “The auditor should issue a contract audit closing statement when (i) a contractor requests final payment on a contract meeting the criteria for quick closeout under FAR 42.708 (also see DCAAM paragraph 6-1010) and (ii) the contracting officer requests DCAA’s advice regarding the final payment and use of quick closeout procedures. This is an application of agreed-upon procedures; follow the guidance in DCAAM paragraph 10-1000, as supplemented in the following paragraphs.  When preparing the closing statement in this situation, the report will clearly indicate what costs and fiscal periods have been audited and which have not been audited.  Suggested wording for the “Scope” paragraph follows:

 

            “This application of agreed-upon procedures is in response to your request for assistance in closing out the contract using the administrative quick closeout procedures under FAR 42.708.  The costs of $___________ claimed on the subject contract represent costs recorded for the contract performance during FYs ______.  Of this amount, $__________ represents amounts incurred during FYs _______.  We have completed the annual audits of incurred costs for these years.  The remaining claimed cost of $__________ were recorded during FY ____.  The audit of [contractor’s name] FY___ incurred costs is in process.  We do not expect that the FY ____ audit results will find a significant exception to the claimed costs.”

 

Once the final audit report is received, contract closeout may proceed as normal.

 

 

Back To TOC

 

 



EARLY CLOSEOUT FOR IDIQ CONTRACTS

 

 

 

Background

 

Early closeout for Task Orders on T&M and LH type IDIQ contracts offers a solution to problems resulting from delays in audit of indirect cost rates. The utilization of early closeout not only allows timely closeout of task orders but the procedure:

 

 

 

The process was initiated as a method for ACOs to close task orders prior to settlement of indirect cost rates.  The practice is acceptable because the task orders are not considered to be individual contracts.  Quick Closeout procedures may be used in conjunction with Early Closeout.  

 

 

Candidates for Early Closeout

 

Candidates for early closeout procedures are those IDIQ contracts that contain FAR Clause 52.232-7. The clause provides the Government the right to withhold 5% of payments otherwise due, up to a maximum of $50,000.  Withholds are directly linked to the contractor release which discharges the Government from all liabilities, obligations and claims.  In addition, withholds are applied against the estimated amount of the entire instrument - not against individual task orders. 

 

ACOs should consider the adequacy of contractor accounting and billing systems.  Adequate systems indicate that minimal adjustments would be required for the final voucher.  If a contractor has inadequacies in their accounting and billing system, the nature of the inadequacy should be considered.

 

 

Early Closeout Procedures

 

While it is recommended that early closeout procedures be established at the on-set of the contract, the procedure may be implemented:

 

 

 

By establishing early closeout procedures at the on-set of the contract, the ACO will be better able to monitor the process in accordance with FAR Clause 52.232-7.

 

The following is offered as a guide in establishing early closeout:

 

 

 

 

 

Detailed early closeout procedures are as follows:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Establishing Early Closeout - After Performance

 

When it is not practical or cost effective for the contractor to submit a completion voucher, a bilateral modification may be executed to administratively close the orders.  The modification would not include those orders held open for withholding purposes.

 

If the ACO is establishing Early Closeout after the fact, the following procedures are recommended:

 

 

 

 

 

 

 

 

 

  

 

Maintaining Early Closeout Records

 

The key to successful execution of early closeout is maintaining information on the orders that were closed by completion vouchers. 

 

Upon physical completion of the last order and settlement of indirect cost rates, the contractor will prepare a final voucher showing a recapitulation of all task order issued. 

 

As part of the review of the final voucher, the ACO should verify billings, payments and in some cases, hours of all delivery order closed under the early closeout process.  Therefore, it is suggested the ACO maintain information regarding:

 

 

 

 

 

If the Contract is Level of Effort (LOE), the ACO should also maintain information regarding:

 

 

 

 

 

 

Early Closeout for Cost Plus Fixed Fee Type Task Orders Issued Under an IDIQ

 

The use of early closeout for cost plus fixed fee type orders issued under an IDIQ contract is considered to be an acceptable practice because the task orders are not considered as individual contracts.  In addition, the clauses governing the closeout process do not prohibit the use of this procedure. 

 

When implementing early closeout for Cost Plus contracts, the ACO should follow the procedures in Early Closeout Procedures and Establishing Early Closeout - After Performance. 

 

FAR Clause 52.216-8, Fixed Fee, states that ". . . the Contracting Officer may withhold further payment of fee until a reserve is set aside . . ." and "This reserve shall not exceed 15 percent of the total fixed fee or $100,000, whichever is less."

 

If the ACO decides to withhold fee, a sufficient number of orders should be held open to maintain the 15% or $100,000 withhold.  This should satisfy the requirements of the FAR clause.  There should be no need to exercise the option of withholding fee for a contractor with a record of timely submission of final cost vouchers and certified final indirect cost proposals, and that complies with other contract terms and conditions. 

 

When an ACO determines that fee withholds are necessary, the ACO should advise the contractor as to the specific reasons why fee withholds are necessary, and should describe the curative measures that the contractor can take to eliminate the need for fee withholds. If the ACO determines that it is necessary to withhold fee to protect the Government's interests, written direction should be issued to the contractor by modification of the contract. The following paragraph provides suggested wording for the modification:

o        This modification is issued to incorporate fee withholding in accordance with FAR Clause 52.216-8 (or -9 or -10, as appropriate).  In order to protect the Government's interest, [contractor] is hereby directed to begin withholding fee from billings under this contract until a reserve is set aside in the amount of $______ (amount of reserve shall not exceed 15% of the total fixed fee or $100,000, whichever is less).  Fee shall be released in accordance with FAR Clause 52.216-8 (or -9 or -10, as appropriate).

 

Back To TOC

 

 


 


RECONCILIATIONS AND SECTION FOUR

 

 

Normally, at the end of the contract the total of funds obligated should match the total payments made to the contractor, inclusive of the final payment. Cost underruns, mistakes in payments, unearned incentives, withheld fees, etc., result in unliquidated obligations at the completion of the contract.  When remaining funds balances or unliquidated obligations exist that can't be explained, reconciliation is required to compare hard copy documents with the MOCAS database.

 

This section covers how to ensure a contract gets into the reconciliation “pipeline" at DFAS.  This requires proper completion and submission of DCMA Form 1797, Request for MOCAS Action/Information and an Obligation Recap. 

 

When all administrative closeout actions are completed, DFAS will assign contracts to MOCAS section 4 upon receipt of a properly completed DCMA Form 1797, Request for MOCAS Action/Information.

 

 

Reconciliation

 

Requests for DFAS action on MOCAS funds reconciliation are submitted on DCMA Form 1797, Request for MOCAS Action/Information.  This form is used both for requests for adjustment and for requests for "full-scope" disbursement reconciliation.

 

 

 

o       Requests for disbursement reconciliation are accompanied by a spreadsheet showing contract obligations to the ACRN level. This includes the identification of all funding obligated/deobligated by the basic contract and all subsequent modifications.  The audit is required to be performed to the Contract Line Item Number (CLIN) and Accounting Classification Record Number (ACRN) levels.

 

o       The ACO signature on the DCMA Form 1797 is the certification that the obligation information is accurate.

 

 

DFAS Columbus is responsible for contract disbursement records and for any adjustments/ corrections to the disbursement records.  When submitting a DCMA Form 1797 requesting reconciliation, DCMA will send an Obligation Recap.  DCMA will not send an audit of the disbursement records.

 

 

Submission of Contract Obligation Data

 

The recommended format for submitting contract obligation data in support of a request for disbursement reconciliation is an Excel spreadsheet.

 

Use of E-Mail for Submitting Requests for Adjustment and Disbursement Reconciliation

 

Requests for adjustment and disbursement reconciliation may be submitted to DFAS via e-mail to DFAS Recon Mail Log cco-reconciliation-maillog@dfas.mil.

 

 

o       Add the appropriate indicator to "MOC_" so that DFAS can identify the DFAS payment division responsible for the reconciliation action -- either "H" for the East Payment Division, "G" for South, or "L" for West.

 

 

MOCAS Delay Reason Code "P"

 

One of the MOCAS section 2 delay reason codes is "P" -- reconciliation with the paying office and contractor being accomplished.  Entry of code "P" into MOCAS does not by itself trigger DFAS action:  If adjustment or disbursement reconciliation is required on "P" coded contracts, the 1797 process shall be used.

 

 

DFAS CAR Reconciliation Report

 

When DFAS receives a DCMA Form 1797 (along with an Obligation Recap) requesting contract reconciliations, the contract is registered in the CAR Recon Report (Open Audit Log).  When DFAS completes the reconciliation, the contract number is posted to the Closed Audit listing.  These reports can be found on the DCMA DFAS Columbus Center Information web page or DFAS Information on the DCMAW MOCAS Bulletin Board.

 

 

Movement of Contracts to MOCAS Section 4

 

MOCAS Part A and B contracts, requiring DFAS disbursement reconciliation are to be assigned to section 4 when the following conditions are met:

 

 

 

 

 

 

 

 

 

 

 

Once all of the above conditions are met, DFAS will assign contracts to MOCAS section 4 upon receipt of a properly completed DCMA Form 1797, Request for MOCAS Action/Information.  The 1797 shall include:

 

 

 

 

 

If the 1797 does not meet the conditions for movement to section 4 as set forth above, DFAS will return the 1797 to the originator and the contract will not be moved to section 4.  Once the conditions are completed, the 1797 will need to be resubmitted as described above.

 

Contracts presently at DFAS for disbursement reconciliation that meet the above criteria can also be moved to section 4 by requesting the move via the 1797 process.  In this case, Part II of the 1797 should include a comment that the contract is registered in the CAR Recon Report (Open Audit Log). 

 

A MOCAS R4 remark will be input by DFAS once the contract is moved to section 4.  It will read “ADMN COMPLT PENDING RECON”. 

 

Most contracts will remain in section 4 until reconciliation and corresponding adjustments are completed and the contract is ready to close.  CAR will close the Part B contracts by issuing a G and F NLA.  DFAS will move Part A contracts to section 2 for closeout and will generate a MOCAS R5/6 remark to read "RECON CMP".  The Part A contracts will receive a G NLA from the CAR clerk, but will require the ACO to issue the F NLA to close the contract.

 

If DFAS' reconciliation reveals that a corrective modification is required, the contract will be moved to section 2 and the ACO will be notified via a DD Form 1716, Contract Data Package Recommendation/ Deficiency Report.  The 1716 will list the corrective action required and will contain the statement   “RECON CMP - MOD REQ FOR CLOSEOUT”.  The MOCAS R5/6 remark will also be updated to include the same statement.  If any other actions are required (i.e. refund) a similar R5/6 remark identifying the required action will be included.

 

Use of electronic 1797s and retention of delivery confirmation is encouraged.  MOCAS coding should be updated as appropriate. 

 

 

Unreconciled Contracts

 

After a contract has been moved to section 4, DFAS Columbus will conduct a Request and Inspection of Documents (RAID).  DFAS will try to locate critical documents required to conduct the audit.   They will perform an extensive search for missing documentation required for the reconciliation.  DFAS may send requests to the ACO, PCO, and Accounting Station asking for assistance in locating the missing documentation.

 

When sufficient documentation cannot be located to support contract reconciliation, a contract will be designated as unreconcilable. Further action to close these contracts will be placed on hold until a mechanism for disposing of the contracts is introduced.

 

 

 

Back To TOC


MOCAS MAINTENANCE OF

BASIC ORDERING AGREEMENTS (BOAs)

AND

INDEFINITE DELIVERY TYPE BASICS (IDTs)

 

 

For Basic Ordering Agreements (BOAs) or Indefinite Delivery Type (IDTs), the Final Delivery Date (FDD) will be the expiration date of the contract/agreement.  When orders are issued under the contract/agreement, the Final Delivery Date (FDD) of the Basic/IDT may be updated to reflect the latest delivery date applicable to any of the orders issued.  If this is done, the ordering period expiration date of the Basic/IDT should be shown on either the R5 or R6 line of the Remarks Data Record.

 

After the ordering period has expired, the Basic can stay in section 1 until all delivery orders are closed. 

 

Upon expiration of the ordering period and closeout of all orders, the ACO shall complete a DD Form 1593 (Contract Administration Completion Form), stating all administrative actions are complete.  The ACO shall request the Trusted Agent move the contract/agreement from CAR section 1 to section 2.  The Trusted Agent should then process closeout via the E-Tool Closeout application or via MOCAS, applying a “G” and “F” NLA in the same cycle.  This will result in the transmission of the PK9/EDI 567 to the PCO.

 

 

Back To TOC

 



REOPENED CONTRACTS IN MOCAS

 

 

Each month contracts reopen because MOCAS data discrepancies were not resolved prior to closure.  The R5 line in MOCAS will show the date the contract was reopened. In many instances, the ACO is not notified when or why these contracts reopen.  A monthly Reopens Profile is posted to the Contract Closeout web page by the 10th of each month which shows the contracts that have reopened the previous month plus a list of all the reopened contracts in MOCAS.

   

The MOCAS Closeout Checklist identifies discrepancies or reasons why contracts reopen (red flags).  The major reasons contracts reopen are open line items, unpaid invoices or unexplained dollars on the ULO line.   DFAS prepares a monthly Research Tool that is posted to the Contract Closeout web page by the 10th of each month.  For each reopened contracts, the Research Tool identifies the reasons why the contract reopened and shows the associated MOCAS screens.  DCMA and DFAS personnel will use this report to manage the reopened contracts, resolve their discrepancies and close the contract.

 

To improve communications, DCMA and DFAS personnel should enter comments in the ACO Notebook field by using the following general format:  date of remarks ddmmyy, remarks, phone number and email address (see Sample ACO Notebook Remarks). 

 

 

Explanations for the R5 remarks field

 

 

Back To TOC


OTHER

 

 

Closing Support Contracts (Part C)

 

On Support Contracts, functional support personnel from the delegated function track performance and completion of all designated activities within MOCAS.  CMO Personnel will input, correct, and close out all support contracts.

 

When all items and services delegated for support have been completed, final updates are made in MOCAS.  When these updates are complete for functional Support Contracts entered into the MOCAS database, functional team personnel perform the MOCAS transaction to move the Support Contract from Section 1 (active) to Section 5 (closed).

 

Corrections/Maintenance of Support Contracts are made through MOCAS YCU2.  Manual closeout of Support contracts is required.

 

 

Payment Only contracts (Assignment Code “G”) are the SOLE responsibility of DFAS for input, change and closeout.   Other than ensuring the ACO code reads "PAY", CMOs should not make changes to, or attempt to close out these contracts since there is no DCMA involvement.

 

Cancelled Unilateral Purchase Orders

Unilateral small purchase orders may be cancelled at no cost to the government via  modification (FAR 13.302-4).  The following procedures apply:

 

·        Cancellation processed in MOCAS and contract remains in section 1:  Forward a DLA Form 1797 to the trusted agent requesting:  manual movement of the contract to CAR Section 2, entry of an R5 Remark “Contract Cancelled per MOD P0000*”, and processing of an NLA G and F to close the contract.

 

·        Cancellation modification not processed or cancellation modification is not on the backlog in MOCAS and the contract remains in CAR Section 1:  Send a DLA Form 1797 to the trusted agent requesting a manual movement of the contract to CAR Section 2, entry of an ACO Notebook Remark “contract cancelled per MOD P0000*, with the cancellation modification attached to be forwarded to DFAS for action. 

             

 

What are current vs expired vs cancelled funds?

 

 

Do not deobligate Cancelled Funds unless they are determined to be “Excess funds” (funds relating to a specific line item or deliverable that was not performed on a contract).

 

 

Differences between replacement and additional funds

 

Replacement funds are those needed to cover cancelled appropriations.  DFAS is responsible for all actions to prevent the need for replacement funds.  If however, replacement funds are required, DFAS is responsible for requesting replacement funds from the funds holder.  When a Final Voucher is submitted and enough funding has been obligated to cover Final Voucher amount, the ACO will use the Final Voucher Review  process and then submit Final Voucher to DFAS.  The voucher will reject for insufficient funds and DFAS will code it “DFAS Merged Account (DMACT)” in the invoicing screen of MOCAS.  DFAS will then request replacement funding from the funding activity.

 

Additional funds involve obligating more money on the contract.  ACOs are responsible for notifying PCOs of the amount of additional funds required to complete the contract.  ACOs will not submit Final Vouchers to DFAS until additional funds have been obligated to the contract via contact modification.

 

Examples:

 

If the funds are current:

 

Obligation = $100

ULO = $25

 

 

If the funds have cancelled):

 

Obligation = $100

ULO = $25

 

 

 

Overpayment – Credit final vouchers

 

If the ACO has any indication that a contractor may owe money to the Government, the ACO shall promptly determine whether an actual debt is due the Government and the amount of the debt.  The ACO shall complete any negotiations regarding debt determinations.  If the ACO and contractor are unable to reach agreement on the existence or amount of a debt the ACO shall make a unilateral debt determination. The ACO shall issue a demand for payment as soon as the ACO has computed the amount of refund due.  For all unilateral debt determinations, the ACO shall issue the demand for payment as a part of the final decision. The ACO shall not offset a debt against amounts otherwise due the contractor instead of issuing a demand for payment. The ACO should encourage the contractor to liquidate debts by lump sum payment.  The ACO shall not compromise or waive a debt.  The department/agency CFOs have sole compromise authority (DFARS 232.616). 

 

ACO and CAs should encourage contractors to use the Automated Cash Collection System (ACCS) to submit refunds/payments to DFAS electronically.  When contracts are ready to close and contractors are required to submit a refund/payment to the Government, they are encouraged to use ACCS to process a credit interim voucher.  After the refund/payment posts to the contract, then the contractor should submit a zero-final voucher to the ACO for review/approval.  Contractors who are unwilling/unable to use ACCs will make check payable to the "Treasury of the United States" and remit the check, along with a copy of the demand for payment, directly to- DFAS Columbus, ATTN:  DFAS-ADPBD/CA, P.O. Box 182249, Columbus, OH 43218-2249.

 

 

EDW 4.0

 

For DCMA, EDW and WAWF are the official file/records management systems for contractual/invoice documents respectively, and replaces the hardcopy 5 part folders.  As such, any document that would normally be filed in hardcopy folders as referenced in the FAR would be placed in EDW and all electronically-submitted invoices are stored in WAWF.

 

Original contract documents will need to be placed into records management as soon as practical but definitely before contract closeout.  Examples of originals (including attachments) that must be records-managed prior to contract closeout include the following:

·        Any document bearing an original signature

·        Correspondence with or without signature requiring action by DCMA

·        ACO issued modifications

·        ACO issued BOA and IDT orders

·        Contract-related E-mail sent by the CMO

·        Contract-related E-mail received by the CMO requiring DCMA action

·        Correspondence generated or altered by the CMO

·        Bilateral agreements: the page(s) showing all signatures

 

DCMA now has a certified system (Open Text eDOCS 6.0) for archiving electronically managed contracts in EDW.  All contracts indicated as closed in EDW will automatically be Records Managed (held for retention and dispose in accordance with the DCMA Records Management.  It is therefore recommended that contracts not be indicated as closed until the contract is at least in Section 5 or greater of MOCAS.

 

The Records Management Officer (Records Officer) is responsible for the disposition of contract folders/documents in eDOCS in accordance with established CMO procedures.

 

 

Wide Area Work Flow (WAWF)

 

Wide Area Workflow (WAWF) is a web-based software application that allows DoD vendors to submit and track their invoices, as well as receipt and acceptance documents electronically.

 

Contractors complete invoices and inspection/acceptance documents interactively on the Internet or submit these documents electronically using EDI or FTP. WAWF-RA notifies the government official automatically of document submission. Once the receipt and acceptance process is complete, payment officials issue payments via appropriate DFAS payment system using Electronic Funds Transfer (EFT). An electronic folder documents the entire process and is accessible to the contractor and authorized federal personnel.

 

 

DCMA/DFAS Partnership Agreement for Operations

The agreement identifies each agency's inputs and outputs for shared process touch-points, establishes indicators that the agencies will use to monitor the health of shared processes and provides the operating principles the agencies will use to facilitate interactions and promote continual shared process improvements.  This agreement succeeds the DCMA/DFAS Concept of Operations (CONOPS).

 

MOCAS Data Sharing Initiative

In May 2002, DCMA initiated an effort to share MOCAS data with selected contractors for the purpose of assisting in resolution/avoidance of payment problems and contract closeout.  Contractors will be provided with data extracts on a monthly basis.  The data is in an electronic format and reflects contract deliveries, payments, obligations, modifications, and similar data. 

Uses for this data may include a comparison of MOCAS data to contractor data to identify discrepancies.  The contractors will investigate the discrepancies between their systems and MOCAS data, make corrections to their own data bases, and identify apparent MOCAS discrepancies to DFAS or the ACO for correction.  Typical discrepancies requiring DFAS or ACO assistance might be modifications not entered, incorrect obligation amounts or missing DD250s.  The ACO's role in this effort will be minimal and should only involve correction of the MOCAS database as appropriate.  

Remedies available to the ACO for delinquent Incurred Cost Claims and Final Vouchers

 

Non-contractual remedies:

 

 

Contractual Remedies:

 

 

 

 Back To TOC


SOLUTIONS FOR PROBLEM CLOSURES

 

 

Background

 

This chapter addresses those "problem closures" that exist in every Contract Management Office.  A "problem closure" is considered to be a contract that has unusual circumstances barring the use of traditional closeout methods. 

 

IMPORTANT!  While this guidebook offers possible closeout solutions, ACOs are encouraged to tailor each of the procedures to fit their individual situation.

 

Examples of circumstances and possible solutions follow:

 

  1. Contractor is No Longer in Business

 

  1. Contractor is Bankrupt

 

  1. Contractor Has Failed to Submit Indirect Cost Data

 

  1. Contractor is Unable to Submit Supporting Indirect Cost Data

 

  1. Contractor Has Failed to Submit Final Invoice/Voucher

 

  1. Negotiated Settlement

 

Traditional closeout procedures are, for the most part, dictated by the payment clauses contained in affected contracts.  When the circumstances mentioned above exist, it is sometimes virtually impossible to close contracts using traditional methods.  In these instances, the ACO shall perform a cost risk analysis and exercise business judgment in accordance with FAR 1.602-2 to ensure that the Government’s interests are protected and administrative actions are reasonable.  With the goal of minimizing loss to the Government, exercising and implementing efficient business practices and processes, the following guidelines are offered as a solution to these "problem closures".

 

Back To TOC

 

 

 

 



CONTRACTOR IS NO LONGER IN BUSINESS

 

Unfortunately, it is not uncommon to have open contracts for companies that are no longer conducting business.  In these instances, the Government shall take every reasonable measure to locate the company and/or its principals.  It is suggested that the ACO:

 

 

 

 

 

 

The contract file should be documented with every attempt made to locate the company and its officials.  If all of the above attempts prove unsuccessful, it is recommended that the ACO begin the Administrative Unilateral Closeout process.

 

Administrative Unilateral Closeout begins with a thorough review of the official contract file(s).  The following should be ascertained during that review:

 

 

 

 

 

 

 

After completing your review, you should notify the PCO of your intent to perform Administrative Unilateral Closeout.  It is recommended that you obtain PCO concurrence prior to issuing an Administrative Unilateral Closeout modification.

 

Recommended actions for Administrative Unilateral Closeout and, if required, determination of final contract price can be found in Contractor Has Failed to Submit Final Invoice/Voucher.

 

 

Back To TOC

 

 

 

 

 



CONTRACTOR IS BANKRUPT

 

 

The ACO should coordinate with counsel on any closeout action. The final contract price should be established at the amount previously paid to the contractor and any excess funds deobligated at the ACRN level.

 

In accordance with FAR 42.9, when notified of bankruptcy proceedings, agencies must, as a minimum --

 

 

 

 

If you discover that the contractor is bankrupt, contact the Office of General Counsel prior to taking any action in furtherance of contract closeout.  A thorough review of the contract and the status of bankruptcy are required.   

 

Once a bankruptcy petition is filed, an automatic stay goes into effect.  This stay generally precludes any action to collect from the debtor or that would interfere with the debtor’s property interests.  Contracts can be considered property of the bankrupt estate. Contract closeout actions could interfere with this property interest and violate the stay.  Consequently, contract closeout actions should generally not be initiated without relief from the stay.  Violation of the stay can subject responsible parties to contempt citations.   DCMA legal offices have been successful in getting relief from stays by working with bankruptcy trustees. 

 

Another reason for immediate coordination with the legal office is that any claim against the contractor must be filed with the court in the form of a Proof of Claim.  With the filing of a bankruptcy petition, the court usually will set a date by which the Proof of Claim must be filed (the Bar Date).  Potential claims against the contractor must be compiled and analyzed to determine whether a Proof of Claim is in the best interests of the Government and, if so, that information must be provided to DFAS.  DFAS has the responsibility for preparing the Proof of Claim and providing it to the cognizant U.S. Attorney for filing with the bankruptcy court.  If the Government doesn’t file a timely proof of claim (a form filed by DFAS establishing us as a creditor), we’re not going to get any money back.  If we missed deadline for filing proof of claim, send 1797 to DFAS seeking write-off (debt not collectible).

 

 

Two types of Bankruptcy the ACO might encounter are:

 

 

Recommended actions for Administrative Unilateral Closeout and, if required, determination of final contract price can be found in Contractor Has Failed to Submit Final Invoice/Voucher.

 

 

 Back To TOC

 


CONTRACTOR HAS FAILED TO SUBMIT INDIRECT COST DATA

 

 

In accordance with FAR 52.216-7 and 52.216-13, the contractor is required to submit a final indirect cost proposal to the Government within the 6-month period following the expiration of each of its fiscal years.  Regardless of whether rates are ACO or Audit determined, it is the ACO’s responsibility to secure certified final rate claims,  pursuant to FAR Part 42.705.  The ACO should work with DCAA to obtain overdue proposals.   Other recommended actions for the ACO:

 

 

 

 

 

The ACO should issue a letter to the contractor ninety days before the end of a contractor's fiscal year, requesting submission of the indirect cost proposal.  If the contractor does not submit their proposal in a timely manner, measures shall be taken to protect the Government's financial interest.  The ACO should issue a letter expressing concern over non-receipt of the proposal.  The letter should include a reminder that failure to submit a proposal is considered to be an internal control deficiency and request a response within 30 days. 

 

If a contractor remains non-responsive, the ACO should work with DCAA on possible actions. 

 

 

Perhaps nothing better captures a contractor’s attention than the unilateral decrementing of the billing rates so as to impede cash flow. This action is not to be punitive in nature, but rather a precautionary step to safeguard the government’s interests in that it is incumbent upon the ACO to preclude overpayments.  Because of the lack of the required rate claim, such concerns may be warranted.  Accordingly, the decrement factor would equate to the reasonable uncertainties related to costs paid or to be paid, as a result thereof.

 

 

More than likely, a contractor will respond to a billing rate decrement.  However, continued non-receipt of incurred cost data dictates an aggressive approach by the ACO.  Contracts are physically complete and the closeout time clock is ticking.

 

Based on these factors, the ACO should proceed with unilateral determination of indirect cost rates (FAR 42.703-2(c)) and/or unilateral determination of final contract price.  (See Contractor Has Failed to Submit Final Invoice/Voucher)

 

 

 

 

Back To TOC

 

 

 

 

 

 



CONTRACTOR IS UNABLE TO SUBMIT SUPPORTING INDIRECT COST DATA

 

 

On rare occasions, contractors are unable to provide final vouchers because they have not retained their financial records for a fiscal year.  When this happens, the contractor does not have the ability to support an audit or the incurred cost previously billed on contracts. 

 

In these instances, Administrative Unilateral Closeout is recommended.  As with all Administrative Unilateral Closeout efforts, a thorough review of the contract file is essential.  You may want to do a risk assessment to ensure the financial security of the contractor.  Upon completion of your review, you should have an understanding as to why the contractor is unable to provide the final voucher.  If Administrative Unilateral Closeout is still deemed suitable under the circumstances, it is recommended that the ACO proceed with the closeout as follows:

 

 

 

 

 

 

The steps outlined above are a summation of the Administrative Unilateral Closeout process and more detailed list of recommended actions for Administrative Unilateral Closeout and, if required, determination of final contract price can be found in Contractor Has Failed to Submit Final Invoice/Voucher.

 

 

Back To TOC

 

 

 



CONTRACTOR HAS FAILED TO SUBMIT FINAL INVOICE/VOUCHER

 

 

Different circumstances and solutions are described below.

 

 

Firm Fixed Price:  Contractor Fails to Submit Final Invoice

 

On occasion, contractors complete performance but fail to submit a final invoice on firm- fixed price contracts.  After making a reasonable number of requests to the contractor, the following actions should be taken.

 

·        Verify that the government has accepted all shipments/performance.

 

·        Send the contractor a letter asking if paid complete or when they will submit final invoice.

 

·        If contractor fails to respond by suspense date in first letter, send a certified letter; return receipt requested, to the contractor advising them of the intent to administratively close the contract.

 

·      If the contractor responds that an amount is owed, but they will not submit a final invoice, the contract should be closed via Final Pay NLA with remaining funds noted on the ACO Notebook.  If the contractor fails to respond by the suspense date in the certified letter, the contract should be closed via Final Pay NLA with remaining funds noted on the ACO Notebook.

 

 

Cost Reimbursable: Contractor Fails to Submit Final Voucher

 

The ACO has the responsibility of obtaining final vouchers and closing documents in accordance with FAR regulations.  The contractor is contractually required to submit final vouchers within 120 days after settlement of final indirect cost rates.  As soon as rates are settled and the contractor has signed an indirect cost rate agreement, the ACO should request that final vouchers be submitted in accordance with FAR 52.216-7(d)(5).

 

In situations where indirect cost rates have been settled and the contractor has failed to adhere to FAR 52.216-7(d)(5), it is recommended that the ACO research and determine the reason for non-submission.  Many times the contractor may not be able to submit final vouchers because:

 

 

 

 

 

 

When the contractor fails to submit a final voucher within 120 days after settlement of final indirect cost rates, and has not provided a reasonable explanation along with an acceptable plan to become current in the submittal of final vouchers and has not received an extension from the ACO, the ACO should take action.  Remedies available to the ACO include: